ICAR AICE-JRF/SRF Project Management, Appraisal & Agri-Entrepreneurship: practice questions

ICAR AICE-JRF/SRF (PhD admission and fellowship) · India · National Testing Agency for ICAR

Original practice questions written to the published syllabus · not past papers
10worked here, free
89written to this exam in this subject
16syllabus units

About ICAR AICE-JRF/SRF

ICAR AICE-JRF/SRF (PhD admission and fellowship) is a PhD, fellowship and lectureship exam run by National Testing Agency for ICAR, for candidates in India. LAN-based CBT, 2 hours, 120 MCQs, 480 marks, +4 / -1. 2026 exam on 4 July 2026. 72 subjects at 122 cities.

Source: cdnbbsr.s3waas.gov.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Project Management, Appraisal & Agri-Entrepreneurship in ICAR AICE-JRF/SRF

Taking an agricultural project from idea to appraisal to delivery, and building an agri-enterprise: feasibility, NPV and IRR, PERT/CPM, business plans and incubation.

Our 89 ICAR AICE-JRF/SRF questions in this subject: 11 easy, 47 medium, 31 hard, across 16 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ICAR AICE-JRF/SRF and are not shown on any other exam's page.

Question 1 · medium

The nominal discount rate is 12% and expected inflation is 5%. What is the exact real discount rate?

  1. 7.00%
  2. 17.60%
  3. 6.67%
  4. 5.00%
Answer and working

C. 6.67%

Fisher relation: real = (1 + nominal)/(1 + inflation) − 1 = 1.12/1.05 − 1 = 6.67%. 7.00% is the simple-subtraction approximation; 17.60% multiplies the two factors instead of dividing; 5% is the inflation rate itself. Real cash flows must be discounted at the real rate.

Question 2 · hard

Two mutually exclusive projects cost 1,000 currency units each. A returns 1,500 currency units in year 3 only (IRR 14.5%). B returns 950 currency units, 150 and 100 in years 1-3 (IRR 15.5%). The opportunity cost of capital is 10%. Which should be chosen and why?

  1. B, because it has the higher IRR
  2. B, because its payback (about 1.3 years) is shorter
  3. Either, because both IRRs exceed 10%
  4. A, because its NPV at 10% (about 127) exceeds B's (about 63)
Answer and working

D. A, because its NPV at 10% (about 127) exceeds B's (about 63)

For mutually exclusive projects rank by NPV at the opportunity cost of capital (or by the IRR of the incremental flows). NPV(A) = 1,500 × 0.7513 − 1,000 = 127; NPV(B) = 63. The NPV curves cross at about 13.8% (the Fisher rate); below that A is better. Ranking by IRR is the classic error because IRR ignores scale and timing differences.

Question 3 · easy

Which probability distribution does PERT assume for the duration of an individual activity?

  1. Poisson distribution
  2. Beta distribution
  3. Binomial distribution
  4. Uniform distribution
Answer and working

B. Beta distribution

The three-point estimate te = (a + 4m + b)/6 derives from the beta distribution, which is bounded and can be skewed. The normal distribution is applied to the total project duration through the central limit theorem, not to each activity.

Question 4 · easy

Which statement correctly contrasts CPM and PERT?

  1. CPM is probabilistic and PERT is deterministic
  2. CPM uses single, known activity times; PERT uses three time estimates to handle uncertainty
  3. CPM applies only to agriculture and PERT only to defence
  4. CPM ignores precedence relationships between activities, while PERT includes them in the network
Answer and working

B. CPM uses single, known activity times; PERT uses three time estimates to handle uncertainty

CPM, developed for plant construction and maintenance with DuPont, assumes deterministic times and adds time-cost trade-offs; PERT, developed for the US Navy's Polaris programme, treats durations as random. Both model precedence.

Question 5 · medium

Which of these is NOT one of the six aspects of project preparation listed by Gittinger?

  1. Institutional-organisational-managerial
  2. Commercial
  3. Political
  4. Economic (efficiency)
Answer and working

C. Political

Gittinger's six aspects are technical; institutional-organisational-managerial; social; commercial; financial; and economic. Political considerations matter in practice but are not one of his analytical aspects.

Question 6 · medium

In a logical framework matrix, what are the four columns?

  1. Goal, purpose, outputs, activities
  2. Inputs, outputs, outcomes and impact, each measured with its own baseline and target values
  3. Narrative summary, objectively verifiable indicators, means of verification, assumptions
  4. Costs, benefits, NPV, IRR
Answer and working

C. Narrative summary, objectively verifiable indicators, means of verification, assumptions

Goal, purpose, outputs and activities are the rows (the hierarchy of objectives). The columns describe each level, how its achievement will be measured, where the evidence comes from, and what external conditions must hold.

Question 7 · medium

A potato cold store is sized to hold the full peak harvest of its catchment. What must its technical and financial projections show that a simple 'rated capacity' figure hides?

  1. The number of potato varieties grown in the catchment and each variety's share of the harvest
  2. The shadow exchange rate
  3. The founder's need for achievement score
  4. Year-wise and season-wise capacity use, since the store will be partly empty much of the year
Answer and working

D. Year-wise and season-wise capacity use, since the store will be partly empty much of the year

Revenue depends on space actually rented over the storage season, not on rated capacity. Projections assuming full utilisation overstate income; the study should show the expected fill rate for each year and season, based on catchment supply and competing stores.

Question 8 · medium

Gittinger warns about a common error in the technical coefficients of agricultural projects. What is it?

  1. Using local rather than international prices for inputs
  2. Including physical contingencies in the cost estimates, which inflates the cost of the project
  3. Assuming research-station yields and rapid adoption rather than realistic on-farm results
  4. Using the with-and-without comparison
Answer and working

C. Assuming research-station yields and rapid adoption rather than realistic on-farm results

Many failed projects rested on yields that farmers never achieved and on adoption schedules that were too fast. Coefficients should come from on-farm evidence with a realistic build-up. Physical contingencies and with-and-without comparisons are good practice.

Question 9 · medium

Which of the following is NOT one of Schumpeter's five types of 'new combinations'?

  1. Introduction of a new good or a new quality of a good
  2. Opening of a new market not previously entered
  3. Conquest of a new source of supply of raw materials
  4. Reducing wages to lower production cost
Answer and working

D. Reducing wages to lower production cost

The five are: a new good or quality; a new method of production; a new market; a new source of raw material or half-manufactured goods; and a new organisation of an industry (creating or breaking a monopoly). Cutting wages is not innovation.

Question 10 · medium

In Clarence Danhof's classification of entrepreneurs, a farmer who adopts a new practice only when failing to do so would clearly cause a loss is called:

  1. Innovative
  2. Fabian
  3. Imitative
  4. Drone
Answer and working

B. Fabian

Danhof, studying American agriculture, identified innovative (introduce new ideas), imitative or adoptive (copy successful innovations), Fabian (very cautious, change only when forced by threat of loss) and drone (refuse to change even at a loss).

A study plan for Project Management, Appraisal & Agri-Entrepreneurship in ICAR AICE-JRF/SRF

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (57% of the 89 questions): CPM and PERT (10, 11%); Discounted measures: NPV, IRR, BCR and profitability index (9, 10%); Social cost-benefit analysis (9, 10%); Incubation, IPR and technology commercialisation (8, 9%); Theories of entrepreneurship and entrepreneurial competencies (8, 9%); Cost overruns, monitoring and mid-course correction (7, 8%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Project risk (7, 8%); Scheduling and resource allocation (6, 7%); Financial and economic feasibility (5, 6%); Market and technical feasibility (4, 4%); The project cycle (4, 4%); Undiscounted measures: payback and ARR (4, 4%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Business plans (2, 2%); Setting up a micro, small or medium enterprise (2, 2%); Time value of money: compounding and discounting (2, 2%); Women's, self-help group and family enterprises (2, 2%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Women's, self-help group and family enterprises (2 hard of 2), Business plans (1 hard of 2), Setting up a micro, small or medium enterprise (1 hard of 2).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: CPM and PERT (4 easy of 10); The project cycle (1 easy of 4).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ICAR AICE-JRF/SRF Project Management, Appraisal & Agri-Entrepreneurship

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers