ICAR AIEEA-PG Project Management, Appraisal & Agri-Entrepreneurship: practice questions

ICAR AIEEA-PG (Master's admission and PG scholarship) · India · National Testing Agency for ICAR

Original practice questions written to the published syllabus · not past papers
10worked here, free
55written to this exam in this subject
15syllabus units

About ICAR AIEEA-PG

ICAR AIEEA-PG (Master's admission and PG scholarship) is a postgraduate admission exam run by National Testing Agency for ICAR, for candidates in India. Computer-based test, 120 minutes, 120 MCQs, +4 / -1 / 0 for unattempted, English only. 2026 exam on 4 July 2026. Fills 30% of Master's seats at agricultural universities.

Source: cdnbbsr.s3waas.gov.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Project Management, Appraisal & Agri-Entrepreneurship in ICAR AIEEA-PG

Taking an agricultural project from idea to appraisal to delivery, and building an agri-enterprise: feasibility, NPV and IRR, PERT/CPM, business plans and incubation.

Our 55 ICAR AIEEA-PG questions in this subject: 34 easy, 20 medium, 1 hard, across 15 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ICAR AIEEA-PG and are not shown on any other exam's page.

Question 1 · easy

In PERT an activity has optimistic time 4 days, most likely 6 days and pessimistic 14 days. What are its expected time and variance?

  1. 8 days and 10.00
  2. 6 days and 1.67
  3. 7 days and 1.67
  4. 7 days and 2.78
Answer and working

D. 7 days and 2.78

te = (a + 4m + b)/6 = (4 + 24 + 14)/6 = 7 days. Variance = [(b − a)/6]^2 = (10/6)^2 = 2.78. 1.67 is the standard deviation, not the variance; 8 is the simple mean of the three estimates.

Question 2 · easy

At which stage of the project cycle does the financing institution independently review the prepared project design?

  1. Identification
  2. Implementation
  3. Ex-post evaluation
  4. Appraisal
Answer and working

D. Appraisal

Preparation is the proponent's job; appraisal is the financier's comprehensive review of the technical, institutional, commercial, financial, economic and social aspects before committing funds.

Question 3 · easy

What is the defining feature of the Delphi method of forecasting?

  1. Regression of demand on price and income
  2. Extrapolation of a linear time trend
  3. Repeated rounds of anonymous expert opinion with feedback until judgements converge
  4. A single face-to-face panel meeting at which experts debate openly until they agree
Answer and working

C. Repeated rounds of anonymous expert opinion with feedback until judgements converge

Delphi keeps experts anonymous so that dominant personalities do not sway the group, and feeds back the group's summary between rounds.

Question 4 · easy

Which economist defined the entrepreneur as an innovator who carries out 'new combinations' and linked this to 'creative destruction'?

  1. Frank Knight
  2. Israel Kirzner
  3. Joseph Schumpeter
  4. Richard Cantillon
Answer and working

C. Joseph Schumpeter

Schumpeter's Theory of Economic Development (1911; English 1934) made innovation the entrepreneur's defining function. Knight emphasised uncertainty-bearing, Kirzner alertness, and Cantillon risk-bearing through buying at certain and selling at uncertain prices.

Question 5 · medium

The Kakinada experiment of the 1960s, reported by McClelland and Winter, is associated with which idea?

  1. Microfinance groups reduce loan default through joint liability and peer monitoring
  2. Achievement motivation training raises entrepreneurial activity
  3. Farmer field schools raise adoption of pest management
  4. Contract farming raises smallholder incomes
Answer and working

B. Achievement motivation training raises entrepreneurial activity

McClelland and Winter (Motivating Economic Achievement, 1969) reported that businessmen in Kakinada, a port town in southern India, given achievement-motivation training subsequently showed more entrepreneurial activity than a comparison group. The study shaped later entrepreneurship development programmes built around achievement motivation.

Question 6 · easy

Which sequence is the most sensible for setting up a small feed mill?

  1. Machinery purchase, registration, feasibility study, trial run, finance
  2. Opportunity screening, feasibility study, choice of legal form and registration, DPR and finance, machinery and staff, trial run, commercial production
  3. Commercial production, DPR, feasibility study, registration
  4. Finance, trial run, opportunity screening, machinery purchase
Answer and working

B. Opportunity screening, feasibility study, choice of legal form and registration, DPR and finance, machinery and staff, trial run, commercial production

Commitments that are hard to reverse (machinery, loans) should follow evidence of feasibility and a legal and financial structure. Starting with machinery is a common and costly mistake.

Question 7 · easy

Which section of a business plan is usually written last although it appears first?

  1. Market and competitor analysis
  2. Operations and production plan
  3. Executive summary
  4. Financial projections
Answer and working

C. Executive summary

The executive summary condenses every other section, so it can be written only when they are complete; investors often read nothing else.

Question 8 · easy

Under the TRIPS Agreement, what is the minimum term of patent protection?

  1. 15 years from grant
  2. 20 years from the filing date
  3. 10 years from filing
  4. 25 years from grant
Answer and working

B. 20 years from the filing date

TRIPS Article 33 sets a minimum term of 20 years counted from the filing date. The 25- and 15-year figures relate to plant variety protection terms in some systems.

Question 9 · medium

On the technology readiness level (TRL) scale, what does level 9 indicate?

  1. Basic principles observed and reported
  2. Laboratory proof of concept
  3. System proven in operation
  4. Prototype demonstrated in a relevant environment
Answer and working

C. System proven in operation

TRLs, developed at NASA, run from 1 (basic principles) to 9 (proven in operation). Proof of concept is around level 3 and prototype demonstration around levels 6-7.

Question 10 · medium

What mainly distinguishes an accelerator from an incubator?

  1. Accelerators usually provide only office space
  2. Incubators invest only in listed companies
  3. Accelerators run short, intensive, cohort-based programmes for ventures already trading, often for equity; incubators support earlier-stage ventures for longer
  4. There is no difference; the terms are legally defined as identical
Answer and working

C. Accelerators run short, intensive, cohort-based programmes for ventures already trading, often for equity; incubators support earlier-stage ventures for longer

Incubators nurture early ventures with space, mentoring and services over a longer period; accelerators compress growth support into a fixed programme ending in a demo day, usually for startups with a product in the market.

A study plan for Project Management, Appraisal & Agri-Entrepreneurship in ICAR AIEEA-PG

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (53% of the 55 questions): Time value of money: compounding and discounting (8, 15%); Discounted measures: NPV, IRR, BCR and profitability index (6, 11%); Theories of entrepreneurship and entrepreneurial competencies (6, 11%); CPM and PERT (5, 9%); Business plans (4, 7%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Incubation, IPR and technology commercialisation (4, 7%); Setting up a micro, small or medium enterprise (4, 7%); Women's, self-help group and family enterprises (4, 7%); Market and technical feasibility (3, 5%); The project cycle (3, 5%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Undiscounted measures: payback and ARR (3, 5%); Financial and economic feasibility (2, 4%); Cost overruns, monitoring and mid-course correction (1, 2%); Project risk (1, 2%); Scheduling and resource allocation (1, 2%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Time value of money: compounding and discounting (1 hard of 8).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Market and technical feasibility (3 easy of 3); Financial and economic feasibility (2 easy of 2).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ICAR AIEEA-PG Project Management, Appraisal & Agri-Entrepreneurship

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers