GARP Sustainability and Climate Risk Certificate Carbon Markets, Offsets & Payments for Ecosystem Services: practice questions
GARP Sustainability and Climate Risk (SCR) Certificate · International · Global Association of Risk Professionals
Original practice questions written to the published syllabus · not past papers
10worked here, free
19written to this exam in this subject
10syllabus units
About GARP Sustainability and Climate Risk Certificate
GARP Sustainability and Climate Risk (SCR) Certificate is a professional certification run by Global Association of Risk Professionals, for candidates worldwide. 80 multiple-choice questions and one multi-part case study, 4 hours, pass/fail. Offered in April and October windows. GARP suggests 100–150 hours of preparation.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
Carbon Markets, Offsets & Payments for Ecosystem Services in GARP Sustainability and Climate Risk Certificate
How carbon is priced and traded and what makes a credit credible: compliance emission trading schemes, Article 6 of the Paris Agreement, voluntary markets, agricultural and land-based project methods, and integrity issues. The economic theory of emissions trading versus taxes is in the Agribusiness subject natural-resource-environmental-economics; this subject covers market design, project methods and integrity in detail.
Our 19 GARP Sustainability and Climate Risk Certificate questions in this subject: 1 easy, 13 medium, 5 hard, across 10 units.
10 practice questions, worked
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to GARP Sustainability and Climate Risk Certificate and are not shown on any other exam's page.
Question 1 · hard
A company sets an internal 'shadow' carbon price for investment appraisal. What does this do?
Charges each business unit a real fee per tonne, which the national tax authority then collects as a levy
Adds a notional cost per tonne to project cash flows so that high-emitting options look less attractive
Creates allowances that the company can sell on the national ETS when its projects cut emissions
Fixes the company's emissions at a cap, beyond which no new projects may be approved for any reason
Answer and working
B. Adds a notional cost per tonne to project cash flows so that high-emitting options look less attractive
A shadow price is a notional cost used in appraisal; no money changes hands. An internal fee is a different design (real transfers within the company, not to a tax authority); neither creates ETS allowances or a hard cap.
Question 2 · medium
What does the EU ETS Market Stability Reserve do?
Fixes the allowance price at a floor set each year by the European Central Bank for all covered sectors
Withdraws allowances from auction when the surplus in circulation is high and releases them when it is low
Holds buffer credits from forestry projects to cover reversals in the EU's land-use sector accounts
Lends allowances to installations that cannot afford to comply, to be repaid with interest within five years
Answer and working
B. Withdraws allowances from auction when the surplus in circulation is high and releases them when it is low
The MSR (operating since 2019) adjusts auction volumes according to the total number of allowances in circulation. It is not a price floor, not a forestry buffer, and not a lending facility.
Question 3 · hard
Australia's reformed Safeguard Mechanism sets declining baselines for large facilities. A facility emits below its baseline. What happens?
It is issued Safeguard Mechanism Credits for the difference, which it may sell to other facilities
Its baseline for later years is raised by the amount of the difference, as a reward for early action
It must pay a carbon tax on the difference, because the scheme charges every tonne below the baseline it sets
Nothing: facilities below baseline are removed from the scheme and lose all rights to trade credits
Answer and working
A. It is issued Safeguard Mechanism Credits for the difference, which it may sell to other facilities
The scheme is baseline-and-credit: SMCs for performance below baseline; facilities above baseline surrender SMCs or ACCUs. Raising baselines, charging tax below baseline, or expelling good performers are not features of it.
Question 4 · medium
The Article 6.4 mechanism issues 100,000 A6.4ERs for a project. 5% go to the Adaptation Fund as share of proceeds and 2% are cancelled for overall mitigation in global emissions (OMGE), both taken at issuance. How many units does the project participant receive?
95,000
98,000
93,000
90,000
Answer and working
C. 93,000
100,000 - 5% (5,000) - 2% (2,000) = 93,000. 95,000 forgets OMGE; 98,000 applies only OMGE (or the old CDM 2%); 90,000 is an invented 10% deduction.
Question 5 · medium
Under ICAO's CORSIA, from 2024 what is the baseline above which international aviation emissions must be offset?
100% of 2019 emissions
100% of 2005 emissions
85% of 2019 emissions
Average of 2019 and 2020
Answer and working
C. 85% of 2019 emissions
From 2024 the CORSIA baseline is 85% of 2019 emissions. The pilot phase (2021-2023) used 2019 emissions; the 2019-2020 average was the original design before COVID-19 distorted 2020; 2005 is an EU-style reference year, not CORSIA's.
Question 6 · medium
Which baseline choice is the most common cause of over-crediting?
A baseline that is updated with observed data from matched control areas over the crediting period
A baseline set conservatively below historical trends to allow for uncertainty
A baseline standardised for a whole jurisdiction and allocated across its projects
A baseline projecting more emissions or deforestation than would really have happened
Answer and working
D. A baseline projecting more emissions or deforestation than would really have happened
Inflated counterfactuals create credits for tonnes that were never at risk. Dynamic, conservative and jurisdictional baselines are responses to that problem.
Question 7 · medium
What did independent studies comparing many voluntary REDD+ projects with synthetic control areas find?
Many project baselines overstated the deforestation that would have occurred, so many credits lacked real reductions
Deforestation inside project areas was higher than in matched control areas, proving that projects increased clearing
No difference could be measured in any project, so remote sensing cannot be used to evaluate REDD+ at all
Project baselines understated deforestation, so projects had received far fewer credits than they deserved
Answer and working
A. Many project baselines overstated the deforestation that would have occurred, so many credits lacked real reductions
Counterfactual studies found substantial over-crediting in many projects, which prompted new methodologies with dynamic and jurisdictional baselines. They did not find general under-crediting, consistently higher clearing inside projects, or that evaluation is impossible.
Question 8 · medium
A wildfire releases 10,000 t CO2 from a forest project whose credits were all sold. The reversal is judged unavoidable. Under typical buffer-pool rules, what happens?
Nothing happens, because credits once issued cannot be affected by later carbon losses
The project developer must buy 10,000 credits on the market and pay a penalty per tonne
10,000 credits are cancelled from the programme's buffer pool to cover the loss
The buyers' retired credits are reinstated and 10,000 of them are re-sold to cover the loss
Answer and working
C. 10,000 credits are cancelled from the programme's buffer pool to cover the loss
Unavoidable reversals are covered by cancelling buffer credits; for avoidable reversals the developer usually must replace them. Retired credits are not un-retired, and ignoring reversals would defeat the buffer's purpose.
Question 9 · medium
Before making any VCMI Claim, what must a company first show?
That all its credits come from removal projects located in the same country as its headquarters
A public science-aligned target with progress against it and transparent emissions reporting
That it has been certified carbon neutral under ISO 14068-1 for at least three consecutive years
That it has retired credits equal to at least 100% of its Scope 1 and 2 emissions in each year
Answer and working
B. A public science-aligned target with progress against it and transparent emissions reporting
VCMI's foundational criteria require a science-aligned near-term target and net-zero commitment, progress and disclosure. Coverage levels define the tier afterwards; there is no removals-only, home-country or ISO 14068-1 prerequisite.
Question 10 · hard
Under Article 6.2, a host country may define the 'first transfer' of ITMOs authorised for other international mitigation purposes (such as CORSIA) as which event?
Only the date the buyer's ship or aircraft leaves the host
Authorisation, issuance or use of the mitigation outcome
Only the year the project was first registered with the CDM
Only the date of the host country's next NDC submission
Answer and working
B. Authorisation, issuance or use of the mitigation outcome
Article 6.2 guidance lets the participating Party specify first transfer as authorisation, issuance or use (or cancellation) for other international mitigation purposes. The other events are invented.
A study plan for Carbon Markets, Offsets & Payments for Ecosystem Services in GARP Sustainability and Climate Risk Certificate
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
First, the heavy units (63% of the 19 questions): Integrity initiatives: core carbon principles and claims guidance (4, 21%); Major compliance markets and their design features (3, 16%); Voluntary carbon market structure: standards, registries, buyers (3, 16%); Carbon pricing instruments: taxes and emission trading schemes (2, 11%).
Read the manual chapters for these first and do every worked question you can find on them.
Then the middle band: From the Kyoto mechanisms (CDM, JI) to Paris Article 6.2 and 6.4 (2, 11%); Avoidance versus removal credits (1, 5%); Corresponding adjustments and double counting (1, 5%); Credit integrity: additionality, baselines, leakage, permanence (1, 5%).
Aim for one sitting per unit, then mixed questions across them.
Then the lighter units: REDD+ and nature-based credits (forest detail in the Forestry track) (1, 5%); Validation, verification and buffer pools (1, 5%).
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Leave time for the hard ones: Corresponding adjustments and double counting (1 hard of 1), Carbon pricing instruments: taxes and emission trading schemes (1 hard of 2), From the Kyoto mechanisms (CDM, JI) to Paris Article 6.2 and 6.4 (1 hard of 2).
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Bank the easy marks: Integrity initiatives: core carbon principles and claims guidance (1 easy of 4).
Do these early in revision so they are fast on the day.
Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.