LAISHA
Open Laisha

State dairy development department posts Dairy Plant Utilities & Energy Management: practice questions

State dairy development department posts · India · State public service commissions (e.g. Kerala PSC)

Original practice questions written to the published syllabus · not past papers
10worked here, free
58written to this exam in this subject
10syllabus units

About State dairy development department posts

State dairy development department posts is a government recruitment exam run by State public service commissions (e.g. Kerala PSC), for candidates in India.

Official site: keralapsc.gov.in.

We have not been able to confirm these details against the exam body's own specification, so fees, dates and pass marks are left out on purpose. Check the current format, eligibility, fees and dates on the official site.

Dairy Plant Utilities & Energy Management in State dairy development department posts

Steam, water, compressed air and electricity in the milk plant, and how to audit and cut energy and water use.

Our 58 State dairy development department posts questions in this subject: 26 easy, 28 medium, 4 hard, across 10 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to State dairy development department posts and are not shown on any other exam's page.

Question 1 · medium

Leaks take 5 kW of compressor power, 8,000 hours a year, with electricity at 8 currency units per kWh. What do they cost each year?

  1. 40,000 currency units
  2. 32,000 currency units
  3. 64,000 currency units
  4. 320,000 currency units
Answer and working

D. 320,000 currency units

5 × 8,000 = 40,000 kWh; × 8 currency units = 320,000. 40,000 currency units forgets the price; the others misplace a factor.

Question 2 · easy

Why do most dairies install two or more boilers?

  1. Because boiler law in most countries bans single-boiler plants
  2. One stays online while another is serviced
  3. To avoid water treatment
  4. To double steam pressure
Answer and working

B. One stays online while another is serviced

Redundancy allows inspection and repair without stopping production and avoids running one boiler at very low load.

Question 3 · medium

Which trap type is usually preferred for a heat exchanger with a modulating steam supply?

  1. Float-and-thermostatic
  2. Bimetallic thermostatic trap set for subcooling
  3. An open drain pipe
  4. Thermodynamic disc
Answer and working

A. Float-and-thermostatic

Float traps discharge condensate continuously at steam temperature and vent air, suiting modulating loads.

Question 4 · easy

Why are steam mains and fittings insulated?

  1. To remove air from the steam space
  2. To make cleaning easier
  3. Less heat loss
  4. To increase steam pressure
Answer and working

C. Less heat loss

Bare pipes lose heat continuously, wasting fuel and adding condensate.

Question 5 · medium

What is the purpose of a backflow preventer or air gap on a water supply?

  1. Increasing water pressure
  2. Softening water
  3. Stopping back-flow into potable lines
  4. Measuring flow to each department for water billing purposes
Answer and working

C. Stopping back-flow into potable lines

Back-siphonage or back-pressure could otherwise pull process or chemical solutions into potable water.

Question 6 · easy

What is a main role of an air receiver?

  1. Drying air below freezing
  2. Making air oil-free for food contact
  3. Buffering demand
  4. Raising pressure above the compressor setting
Answer and working

C. Buffering demand

Receivers store air to smooth demand and let water settle for draining.

Question 7 · medium

How is a low power factor usually corrected?

  1. Capacitor banks
  2. Larger cables
  3. Raising the supply voltage
  4. Adding motors
Answer and working

A. Capacitor banks

Capacitors supply reactive power locally, cutting kVA drawn from the grid.

Question 8 · medium

What are IE3 and IE4?

  1. Boiler pressure classes
  2. Insulation classes for cables
  3. Air purity grades
  4. Motor efficiency classes
Answer and working

D. Motor efficiency classes

International efficiency classes for motors; higher numbers mean higher efficiency.

Question 9 · medium

In a liquid milk plant, which is often the largest electrical user?

  1. Gate barriers
  2. Office lighting and computers
  3. Packing machine heaters
  4. Refrigeration
Answer and working

D. Refrigeration

Refrigeration for chilling and cold storage commonly leads electrical use.

Question 10 · medium

How is solar thermal heat usually integrated into dairy heating?

  1. Preheating water, with storage
  2. Driving air compressors
  3. Replacing the boiler entirely in all seasons
  4. Superheating steam
Answer and working

A. Preheating water, with storage

Variable solar supply is buffered in storage and topped up by conventional heat.

A study plan for Dairy Plant Utilities & Energy Management in State dairy development department posts

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (48% of the 58 questions): Water conservation and reuse (8, 14%); Electrical supply and power factor (7, 12%); Energy audits (7, 12%); Boiler and pressure-vessel safety rules (6, 10%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Boilers: types, fittings, mountings and efficiency (6, 10%); Compressed air systems (6, 10%); Water supply, treatment and quality for dairy use (6, 10%); Renewable energy in dairy plants: solar thermal, biogas (5, 9%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Steam distribution and condensate recovery (4, 7%); Heat recovery and cogeneration (3, 5%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Boiler and pressure-vessel safety rules (1 hard of 6), Electrical supply and power factor (1 hard of 7), Energy audits (1 hard of 7).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Boilers: types, fittings, mountings and efficiency (4 easy of 6); Boiler and pressure-vessel safety rules (3 easy of 6).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — State dairy development department posts Dairy Plant Utilities & Energy Management

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.