ICAR AIEEA-PG Dairy Plant Design, Layout & Project Engineering: practice questions

ICAR AIEEA-PG: Dairy Science (group 16) and Dairy Technology (group 17) · India · NTA for ICAR

Original practice questions written to the published syllabus · not past papers
10worked here, free
68written to this exam in this subject
9syllabus units

About ICAR AIEEA-PG

ICAR AIEEA-PG: Dairy Science (group 16) and Dairy Technology (group 17) is a postgraduate admission exam run by NTA for ICAR, for candidates in India. Computer-based, 2 hours, 120 multiple-choice questions, +4 for a correct answer and −1 for a wrong one (2026 bulletin). One paper per major subject group.

Source: icar.org.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Dairy Plant Design, Layout & Project Engineering in ICAR AIEEA-PG

Dairy plant layout and design, functional design and space requirement, sanitary equipment and plant hygiene. Expect questions on layout principles and flow patterns, location factors, the sequence of operations in milk and product sections, functional areas and their adjacencies, holding tube and regeneration, and simple capacity and tank-sizing calculations.

Planning a dairy plant from product mix to building: location, layout, equipment sizing, pressure vessels, costing and commissioning.

Our 68 ICAR AIEEA-PG questions in this subject: 25 easy, 35 medium, 8 hard, across 9 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ICAR AIEEA-PG and are not shown on any other exam's page.

Question 1 · easy

In steady continuous processing with no reaction, which statement of the mass balance is correct?

  1. Mass in exceeds mass out by the water lost
  2. Only the total balances; components need not
  3. In equals out, in total and for each component
  4. Mass out exceeds mass in by the product formed
Answer and working

C. In equals out, in total and for each component

At steady state nothing accumulates, so inputs equal outputs both in total and component by component (fat, SNF, water) when no reaction creates or destroys them. Water lost in evaporation is itself an output stream.

Question 2 · easy

What is a schedule of accommodation in functional design?

  1. A shift roster showing when each room is staffed
  2. A list of every room with its area and needs
  3. A timetable for cleaning each room in the plant
  4. A list of equipment suppliers with delivery dates
Answer and working

B. A list of every room with its area and needs

The schedule of accommodation lists each functional area with its floor area, height, environment, hygiene level, drainage and services. It is the brief for the architect and engineers, not a staffing or cleaning timetable.

Question 3 · easy

Which pair of areas should a relationship chart mark as needing to be close in a liquid milk plant?

  1. Chemical store and filling room
  2. Toilets and pasteurised milk tanks
  3. Filling room and cold store
  4. Raw milk reception and filling room
Answer and working

C. Filling room and cold store

Packed product should move directly from filling into the cold store. Chemicals must be kept away from exposed product, toilets must not open into production, and raw reception must be kept apart from filling to protect processed product.

Question 4 · medium

A machine has a footprint of 2 m by 1 m and needs 1 m of clear space on every side. What floor area should be allowed for it?

  1. 12 square metres
  2. 2 square metres
  3. 6 square metres
  4. 8 square metres
Answer and working

A. 12 square metres

With 1 m on each side, the space is (2 + 2) × (1 + 2) = 4 × 3 = 12 m². 2 m² is the footprint alone; 6 m² adds clearance on one side only; 8 m² adds 2 m to one dimension only.

Question 5 · medium

Why must clear height be considered as carefully as floor area in a dairy processing hall?

  1. Higher ceilings always reduce the plant's refrigeration load
  2. Tall equipment, bowl removal and overhead pipe racks need vertical space
  3. Building codes everywhere fix the same height for all food plants
  4. Clear height matters only for offices and laboratories
Answer and working

B. Tall equipment, bowl removal and overhead pipe racks need vertical space

Silos, separators that need head room to lift the bowl, and pipe racks set the height, and powder plants need very tall buildings for driers. Higher ceilings usually increase the air volume to condition, and height rules vary by country.

Question 6 · easy

Where should the milk testing laboratory be placed in relation to reception?

  1. Beside the dispatch dock, so finished product is tested first
  2. Inside the filling room, so testing staff watch the fillers
  3. Next to it, so samples are tested before milk is accepted
  4. In the office block, far from all processing areas
Answer and working

C. Next to it, so samples are tested before milk is accepted

Testing incoming milk before it is pumped into silos lets the plant reject unacceptable milk. A laboratory inside the filling room would bring raw samples into a high-hygiene area.

Question 7 · medium

Which item is part of a tanker reception bay in a modern dairy plant?

  1. A can tipping trough for ten-litre cans
  2. A tanker cleaning station
  3. A churn for making butter from rejected milk
  4. A cold store for packed finished product
Answer and working

B. A tanker cleaning station

Tankers are cleaned at the plant after unloading so they return clean to collection routes. Can tipping belongs to can reception, and churns and cold stores belong to other sections. The station cleans tankers after unloading so they leave clean.

Question 8 · hard

Why should packaging materials be de-boxed in a separate area before entering production rooms?

  1. Packaging must be weighed in a separate room by law in every country
  2. Removing boxes in production rooms slows down the fillers
  3. De-boxing lets packaging warm up to room temperature first
  4. Outer cartons carry dust and pests and should not enter clean areas
Answer and working

D. Outer cartons carry dust and pests and should not enter clean areas

Outer cartons travel through warehouses and trucks and bring dust, insects and microorganisms. Removing them outside production protects clean areas. Legal weighing and warming are not the reason.

Question 9 · medium

Why is a holding tube sized on the fastest particle rather than the mean velocity?

  1. Every particle must be held for at least the full time
  2. The mean velocity cannot be measured in a closed tube
  3. The fastest particle carries the most fat in whole milk
  4. Regulators require tubes twice as long as calculated
Answer and working

A. Every particle must be held for at least the full time

Flow is faster at the centre of the tube, so sizing on the mean would let the fastest milk pass in less than the required time. The design uses the maximum velocity, about 1.2 times the mean in turbulent flow and 2 times in laminar flow.

Question 10 · medium

Which attack must a dairy processing floor resist that is less important in a dry warehouse?

  1. Lactic acid from spilled milk, plus cleaning acids and alkalis
  2. Ultraviolet light from roof skylights fading the colour
  3. Freezing from outside air in all seasons
  4. Abrasion by paper and cardboard packaging alone
Answer and working

A. Lactic acid from spilled milk, plus cleaning acids and alkalis

Spilled milk sours to lactic acid, and cleaning uses hot acids and alkalis with thermal shock, so floors need acid-resistant tiles or resistant resin systems.

A study plan for Dairy Plant Design, Layout & Project Engineering in ICAR AIEEA-PG

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (35% of the 68 questions): Building, floors, drains and services (8, 12%); Equipment sizing and selection (8, 12%); Functional design and space requirements (8, 12%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Hygienic zoning and personnel flow (8, 12%); Installation, commissioning and validation (8, 12%); Layout of reception, processing, packing and storage areas (8, 12%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Process flow diagrams and mass balances (8, 12%); Plant location and site selection (6, 9%); Product mix and capacity planning (6, 9%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Equipment sizing and selection (2 hard of 8), Building, floors, drains and services (1 hard of 8), Functional design and space requirements (1 hard of 8).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Plant location and site selection (4 easy of 6); Functional design and space requirements (4 easy of 8).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ICAR AIEEA-PG Dairy Plant Design, Layout & Project Engineering

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.