ICAR AICE-JRF/SRF Dairy Plant Design, Layout & Project Engineering: practice questions

ICAR AICE-JRF/SRF (PhD): Dairy Chemistry, Dairy Microbiology, Dairy Technology, Dairy Engineering · India · NTA for ICAR

Original practice questions written to the published syllabus · not past papers
10worked here, free
32written to this exam in this subject
11syllabus units

About ICAR AICE-JRF/SRF

ICAR AICE-JRF/SRF (PhD): Dairy Chemistry, Dairy Microbiology, Dairy Technology, Dairy Engineering is a PhD, fellowship and lectureship exam run by NTA for ICAR, for candidates in India.

Source: icar.org.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Dairy Plant Design, Layout & Project Engineering in ICAR AICE-JRF/SRF

Process equipment and pressure vessel design: thin-shell stresses, design thickness of shells and heads, head types, supports, codes and corrosion allowance, together with equipment sizing. Expect derivation-style and numerical questions at a higher level, and comparisons of head shapes and design choices.

Planning a dairy plant from product mix to building: location, layout, equipment sizing, pressure vessels, costing and commissioning.

Our 32 ICAR AICE-JRF/SRF questions in this subject: 3 easy, 10 medium, 19 hard, across 11 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ICAR AICE-JRF/SRF and are not shown on any other exam's page.

Question 1 · hard

Why do utility peaks in a dairy plant often coincide with cleaning periods?

  1. Cleaning stops all production, so every utility reaches zero
  2. Cleaning uses only cold water, which lowers steam demand
  3. Refrigeration must be switched off whenever any line is cleaned
  4. Hot detergent and rinse water are drawn while other lines keep producing
Answer and working

D. Hot detergent and rinse water are drawn while other lines keep producing

CIP draws heated water and detergent and large rinse volumes, while other lines continue processing, so steam and water demand peak together. Production does not stop everywhere during cleaning, and hot cleaning raises steam demand.

Question 2 · hard

A plant has condensation dripping from cold pipes above an open filler. Which design response addresses the cause?

  1. Raise the filler's speed so less product is exposed to each drip
  2. Increase the frequency of finished-product testing at the filler
  3. Fit a wider drip tray under the filler to catch spilled product
  4. Improve ventilation and insulate or reroute the cold pipes away from open product
Answer and working

D. Improve ventilation and insulate or reroute the cold pipes away from open product

Condensation forms when warm humid air meets cold surfaces; ventilation, insulation and routing cold pipes away from open product remove the source. Faster filling, more testing and drip trays do not stop drips falling onto product.

Question 3 · hard

Why is hygienic zoning decided at the layout stage rather than after the building is designed?

  1. Zoning only affects the colour of staff uniforms, which can change any time
  2. Auditors refuse to inspect zoning that was planned after construction
  3. It sets walls, air handling, drains and changing rooms, hard to alter later
  4. It is decided by the equipment supplier, who must know it before ordering
Answer and working

C. It sets walls, air handling, drains and changing rooms, hard to alter later

Zones determine physical features of the building: partition walls, air handling with pressure cascades, drain routes and changing facilities. Retrofitting them in a finished building is expensive. Uniform colours follow zoning, they do not define it.

Question 4 · easy

Compared with a cylinder of the same diameter and wall thickness, what is the membrane stress in a sphere under the same internal pressure?

  1. Twice the cylinder's hoop stress
  2. Equal to the cylinder's hoop stress
  3. One quarter of the cylinder's hoop stress
  4. Half the cylinder's hoop stress
Answer and working

D. Half the cylinder's hoop stress

A sphere's stress is PD/(4t) in all directions, half the cylinder's hoop stress PD/(2t). That is why hemispherical heads need about half the thickness of the shell.

Question 5 · medium

Why are flat heads rarely used on vessels with significant internal pressure?

  1. They cannot be welded to a cylindrical shell at all
  2. They are banned by every pressure vessel code in force
  3. They bend under pressure and need very great thickness
  4. They make the vessel impossible to drain completely
Answer and working

C. They bend under pressure and need very great thickness

A flat plate resists pressure by bending, so it needs much more thickness than a curved head, which resists pressure mainly by membrane tension. Flat heads are used for low pressures or small diameters and can be welded and permitted under codes.

Question 6 · medium

What is a corrosion allowance in pressure vessel design?

  1. Extra thickness added for metal lost in service
  2. A discount on vessel price for buyers who accept corroded plate
  3. The time allowed between internal inspections of the vessel
  4. A coating that prevents all corrosion of stainless steel
Answer and working

A. Extra thickness added for metal lost in service

The required thickness from the stress formula is increased by an allowance for expected metal loss over the vessel's life; the plate ordered is the next standard size above the total. The calculated thickness from the stress formula is the starting point; the allowance is added to it.

Question 7 · hard

What must a hygienic dairy pressure vessel's supports satisfy in addition to the pressure code?

  1. Be painted the same colour as the vessel for easy identification
  2. Allow floor cleaning beneath and avoid crevices that trap soil
  3. Be made of mild steel so that they rust visibly when damaged
  4. Be welded directly into the floor drain for maximum stability
Answer and working

B. Allow floor cleaning beneath and avoid crevices that trap soil

Legs and supports must leave space to clean the floor and must not create crevices or ledges, so hygienic design rules apply alongside the structural ones. Rusting supports and supports set into drains are unhygienic.

Question 8 · hard

A pump moves 30 cubic metres per hour of a liquid of density 1,000 kg/m³ against a total head of 25 m with 65 percent efficiency. What shaft power is needed?

  1. About 2.0 kW
  2. About 4.8 kW
  3. About 3.1 kW
  4. About 1.3 kW
Answer and working

C. About 3.1 kW

Hydraulic power = ρgQH = 1,000 × 9.81 × (30/3,600) × 25 = 2.04 kW; shaft power = 2.04 ÷ 0.65 = 3.1 kW. 2.0 kW ignores efficiency; 4.8 kW divides twice; 1.3 kW multiplies by efficiency instead of dividing.

Question 9 · medium

Why are services routed through service corridors or external pipe bridges where possible?

  1. Pipes in corridors need no insulation in any climate
  2. It halves the length of every pipe in the plant
  3. Regulations forbid any pipe inside a production room
  4. Maintenance staff can work on them without entering high-hygiene rooms
Answer and working

D. Maintenance staff can work on them without entering high-hygiene rooms

Keeping valves, unions and services outside high-hygiene rooms reduces traffic and contamination risk during maintenance. Pipe lengths and insulation needs are not reduced by this, and some pipes must enter production rooms.

Question 10 · medium

Why are internal welds on dairy product pipelines inspected, for example with a borescope?

  1. Inspection makes the pipe stronger under pressure
  2. Borescopes measure the flow rate through the line
  3. Internal welds determine the colour of the product
  4. A poor internal weld leaves an uncleanable crevice
Answer and working

D. A poor internal weld leaves an uncleanable crevice

Lack of penetration or rough internal welds leave crevices where soil and bacteria lodge and CIP cannot reach. Inspection finds them before the line enters service.

A study plan for Dairy Plant Design, Layout & Project Engineering in ICAR AICE-JRF/SRF

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (66% of the 32 questions): Pressure vessel design: codes, shells, heads and supports (11, 34%); Installation, commissioning and validation (4, 13%); Equipment sizing and selection (3, 9%); Process flow diagrams and mass balances (3, 9%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Building, floors, drains and services (2, 6%); Functional design and space requirements (2, 6%); Hygienic zoning and personnel flow (2, 6%); Product mix and capacity planning (2, 6%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Layout of reception, processing, packing and storage areas (1, 3%); Plant location and site selection (1, 3%); Project costing, feasibility and detailed project reports (1, 3%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Equipment sizing and selection (3 hard of 3), Hygienic zoning and personnel flow (2 hard of 2), Product mix and capacity planning (2 hard of 2).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Pressure vessel design: codes, shells, heads and supports (3 easy of 11).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ICAR AICE-JRF/SRF Dairy Plant Design, Layout & Project Engineering

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.