Nepal Engineering Council Registration Exam Bio-energy Systems: Design & Applications: practice questions

Nepal Engineering Council Registration Exam — Agricultural Engineering · Nepal · Nepal Engineering Council

Original practice questions written to the published syllabus · not past papers
10worked here, free
32written to this exam in this subject
13syllabus units

About Nepal Engineering Council Registration Exam

Nepal Engineering Council Registration Exam — Agricultural Engineering is a licensing and registration exam run by Nepal Engineering Council, for candidates in Nepal.

Official site: nec.gov.np.

We have not been able to confirm these details against the exam body's own specification, so fees, dates and pass marks are left out on purpose. Check the current format, eligibility, fees and dates on the official site.

Bio-energy Systems: Design & Applications in Nepal Engineering Council Registration Exam

Turning crop residues, dung and oils into fuel: briquettes, gasifiers, biogas plants and liquid biofuels, and auditing farm energy.

Our 32 Nepal Engineering Council Registration Exam questions in this subject: 8 easy, 19 medium, 5 hard, across 13 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Nepal Engineering Council Registration Exam and are not shown on any other exam's page.

Question 1 · medium

A tumbling-box (or rotating drum) test on pellets or briquettes is used to measure:

  1. Gross calorific value
  2. Ash fusion temperature
  3. Equilibrium moisture content of the pellets after tumbling in humid air for a set time
  4. Mechanical durability: the share surviving handling without breaking into fines
Answer and working

D. Mechanical durability: the share surviving handling without breaking into fines

Durability testing tumbles a known mass for a set number of revolutions, sieves out fines, and reports the mass retained as a percentage. Low durability means dust, losses and feeding problems in stoves and boilers. Calorific value needs a bomb calorimeter and ash fusion needs a heated microscope or furnace test.

Question 2 · medium

A gasifier–engine–generator set delivers 20 kW of electricity with an overall biomass-to-electricity efficiency of 20% (LHV basis). Biomass LHV is 15 MJ/kg. The biomass consumption and specific fuel consumption are:

  1. 0.96 kg/h and 0.05 kg/kWh
  2. 24 kg/h and 1.2 kg/kWh
  3. 4.8 kg/h and 0.24 kg/kWh
  4. 6.67 kg/h and 0.33 kg/kWh
Answer and working

B. 24 kg/h and 1.2 kg/kWh

Fuel power = 20 ÷ 0.2 = 100 kW = 360 MJ/h. Biomass = 360 ÷ 15 = 24 kg/h. Specific consumption = 24 ÷ 20 = 1.2 kg/kWh, within the 1–1.5 kg/kWh range commonly reported for small woody-biomass systems. Ignoring the efficiency gives the fuel for a perfect converter.

Question 3 · hard

The most serious safety hazard specific to operating a producer-gas plant in an enclosed shed is:

  1. Hydrogen sulphide explosion from the ash pit when hot, wet ash is quenched with water
  2. Carbon monoxide poisoning from gas leaks at start-up, shut-down or filter servicing
  3. Radiation from the gasifier throat
  4. Oxygen enrichment of the shed air
Answer and working

B. Carbon monoxide poisoning from gas leaks at start-up, shut-down or filter servicing

Producer gas typically contains about 15–25% CO, a colourless, odourless and highly toxic gas. Plants need good ventilation, flares for start-up gas, CO detectors and procedures that never let operators work on open gas lines alone. Explosion risk also exists when air leaks into gas spaces, but CO exposure is the chronic, specific danger.

Question 4 · easy

The mesophilic temperature range, within which most farm biogas plants operate, is about:

  1. 10–20 °C
  2. 30–40 °C (optimum near 35–37 °C)
  3. 50–60 °C (the thermophilic range)
  4. 70–80 °C
Answer and working

B. 30–40 °C (optimum near 35–37 °C)

Mesophilic digestion runs at about 30–40 °C. Thermophilic digestion (about 50–60 °C, often 55 °C) is faster and destroys more pathogens but is less stable and needs heating. Below about 20 °C (psychrophilic) gas production is slow, which is why unheated plants in cold regions or winters need longer retention times.

Question 5 · easy

In a floating-drum biogas plant, the gas is delivered at:

  1. A pressure that usually rises steadily as gas accumulates
  2. A nearly constant pressure
  3. Atmospheric pressure, so a blower is always needed
  4. A pressure set by the height of the inlet pipe
Answer and working

B. A nearly constant pressure

The gas holder floats on the slurry (or in a water jacket) and rises as gas collects; the pressure equals the drum's weight divided by its area and stays nearly constant. In a fixed-dome plant, pressure rises as gas displaces slurry into the outlet chamber, so pressure varies with the amount of stored gas.

Question 6 · medium

Compared with a floating-drum (KVIC-type) plant of the same capacity, a fixed-dome plant (Janata or Deenbandhu type) generally has:

  1. Constant gas pressure and a steel gas holder that must be painted every year against corrosion
  2. Higher capital cost and a shorter life because the whole structure sits above ground
  3. Lower cost and no moving steel parts, but variable gas pressure and a need for skilled masonry
  4. No need for an outlet or displacement chamber
Answer and working

C. Lower cost and no moving steel parts, but variable gas pressure and a need for skilled masonry

Fixed-dome plants are built of brick or concrete, usually underground; the dome stores gas by pushing slurry into a displacement (outlet) chamber, so pressure varies. With no steel drum they are cheaper and long-lived, but cracks in the dome leak gas and are hard to repair. Floating-drum plants give constant pressure and a visible gas store but the steel drum corrodes and needs maintenance.

Question 7 · medium

The Deenbandhu biogas plant, developed in India in the 1980s, reduced cost compared with the earlier Janata fixed-dome design mainly by:

  1. Replacing masonry with a floating steel drum
  2. Using a geometry made of spherical segments that reduces the masonry surface area for a given volume
  3. Omitting the outlet chamber so slurry leaves through the gas pipe
  4. Operating at thermophilic temperature so the digester can be smaller
Answer and working

B. Using a geometry made of spherical segments that reduces the masonry surface area for a given volume

Spherical shapes enclose the most volume for the least surface, so less brick and cement are needed. The Deenbandhu design (developed by a voluntary agency, AFPRO) was cheaper than the Janata design and was widely adopted in India's national biogas programme. It is still a fixed-dome, unheated, mesophilic plant.

Question 8 · easy

A digester of 8 m³ active volume receives 0.2 m³ of slurry per day. Its hydraulic retention time is:

  1. 1.6 days
  2. 40 days
  3. 0.025 days
  4. 20 days
Answer and working

B. 40 days

HRT = volume ÷ daily flow = 8 ÷ 0.2 = 40 days. It is the average time a parcel of slurry spends in the digester. 1.6 days multiplies instead of dividing; 0.025 days inverts the ratio; 20 days takes the daily flow as 0.4 m³ by adding the 1:1 dilution water again.

Question 9 · hard

A village cooperative plans to make biodiesel from used frying oil with a high free fatty acid content. The most suitable process choice is:

  1. A single alkali step with extra sodium hydroxide added to neutralise all of the free fatty acid
  2. Direct blending of the used oil with diesel without treatment
  3. Acid-catalysed esterification of the FFA, then alkali transesterification, using dried oil
  4. Fermenting the oil with yeast
Answer and working

C. Acid-catalysed esterification of the FFA, then alkali transesterification, using dried oil

Adding extra alkali turns FFA into soap, which emulsifies the product and cuts yield, and water in the oil hydrolyses esters to more FFA. The two-step route converts FFA to esters with an acid catalyst (for example sulphuric acid with methanol), then completes transesterification with a base. Methanol is toxic and flammable, so safe storage and ventilation are part of the design.

Question 10 · medium

The first step in a walk-through energy audit of a rice mill is to:

  1. Gather energy and production records (bills, husk use) and map the main energy-using equipment
  2. Replace all motors and pumps with the highest-efficiency (IE4) models available before taking readings
  3. Install a biomass gasifier
  4. Calculate the energy ratio of the paddy crop
Answer and working

A. Gather energy and production records (bills, husk use) and map the main energy-using equipment

An audit starts by establishing a baseline: how much energy of each kind is used, where, and per tonne of output (specific energy consumption). That shows where the large losses are, such as boiler and parboiling steam, dryer furnaces or oversized motors, before any investment is chosen. Replacement decisions come after measurement and economic analysis.

A study plan for Bio-energy Systems: Design & Applications in Nepal Engineering Council Registration Exam

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (66% of the 32 questions): Biogas plant sizing and gas yield (7, 22%); Anaerobic digestion stages (5, 16%); Biogas plant types: floating drum and fixed dome (5, 16%); Biodiesel and transesterification (2, 6%); Briquetting and pelleting (2, 6%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Energy audit and energy ratio in agriculture (2, 6%); Gasification: updraft and downdraft gasifiers (2, 6%); Producer gas and dual-fuel engines (2, 6%); Bio-ethanol (1, 3%); Biomass characterisation: proximate and ultimate analysis (1, 3%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Calorific value (1, 3%); Combustion of biomass (1, 3%); Pyrolysis (1, 3%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Combustion of biomass (1 hard of 1), Biodiesel and transesterification (1 hard of 2), Gasification: updraft and downdraft gasifiers (1 hard of 2).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Anaerobic digestion stages (3 easy of 5); Briquetting and pelleting (1 easy of 2).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Nepal Engineering Council Registration Exam Bio-energy Systems: Design & Applications

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.