ASRB NET Statistical Quality Control & Reliability: practice questions

ASRB NET - Agricultural Statistics (and Computer Application / Bioinformatics) · India · Agricultural Scientists Recruitment Board (ICAR)

Original practice questions written to the published syllabus · not past papers
10worked here, free
35written to this exam in this subject
10syllabus units

About ASRB NET

ASRB NET - Agricultural Statistics (and Computer Application / Bioinformatics) is a professional certification run by Agricultural Scientists Recruitment Board (ICAR), for candidates in India. NET: one objective paper of about 150 questions, 2 hours, negative marking, online, Master's level (pattern as reported for other disciplines).

Official site: asrb.org.in.

We have not been able to confirm these details against the exam body's own specification, so fees, dates and pass marks are left out on purpose. Check the current format, eligibility, fees and dates on the official site.

Statistical Quality Control & Reliability in ASRB NET

Applied choice and interpretation of charts, capability indices and sampling plans.

Monitoring and accepting quality: Shewhart charts for variables and attributes, CUSUM and EWMA charts, process capability, acceptance sampling plans with their OC, AOQ and ATI curves, and reliability models, applied to seed testing, food processing and input quality. The Agricultural Engineering track covers control charts briefly; this is the full subject.

Our 35 ASRB NET questions in this subject: 2 easy, 25 medium, 8 hard, across 10 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ASRB NET and are not shown on any other exam's page.

Question 1 · medium

Several Western Electric run rules are added to a Shewhart chart. What happens to the in-control ARL?

  1. It rises above 370
  2. It falls well below 370
  3. It becomes infinite
  4. It stays at 370
Answer and working

B. It falls well below 370

Extra rules catch small shifts sooner but also create more false alarms, so ARL₀ drops.

Question 2 · medium

Why are subgroups of five consecutive bags from one filling head used, rather than five bags from different heads?

  1. To make the subgroup mean normally distributed
  2. Rational subgrouping
  3. To increase the false-alarm rate
  4. Because standards require exactly five bags
Answer and working

B. Rational subgrouping

Mixing heads inside a subgroup inflates within-subgroup variation, widening limits and hiding head-to-head differences.

Question 3 · medium

A dairy laboratory has one fat reading per batch, slightly skewed, and wants to detect slow drifts. Which chart suits it?

  1. A p chart with n = 1
  2. An R chart
  3. An EWMA chart
  4. A c chart
Answer and working

C. An EWMA chart

EWMA averaging makes it robust to mild non-normality and sensitive to small drifts with individual data.

Question 4 · medium

Fat, protein and lactose in milk are monitored together. What controls the overall false-alarm rate and detects changes in combinations?

  1. Three R charts
  2. A Hotelling T² chart
  3. Three separate p charts
  4. A c chart on the total
Answer and working

B. A Hotelling T² chart

Separate charts inflate the joint false-alarm rate and miss shifts in correlated combinations; T² or MEWMA charts handle both.

Question 5 · hard

How do Pp and Ppk differ from Cp and Cpk?

  1. They ignore the process mean
  2. They use specification limits at ±6σ
  3. They apply only to attribute data
  4. They use the overall σ
Answer and working

D. They use the overall σ

Cp and Cpk use within-subgroup σ (R̄/d₂); performance indices use overall σ and are smaller when the process drifts.

Question 6 · medium

A firm uses single plans from ISO 2859-1 but ignores its switching rules. What is the consequence?

  1. Consumer protection is weakened
  2. Nothing; switching is optional
  3. The plans become variables plans
  4. Producer's risk falls to zero
Answer and working

A. Consumer protection is weakened

The scheme's protection comes from switching to tightened inspection after poor lots; single plans alone are lenient at poor quality.

Question 7 · hard

Why are c = 0 plans less protective of producers than they look?

  1. They accept every lot
  2. They require 100% inspection
  3. Their AOQ is always zero
  4. Good lots get rejected
Answer and working

D. Good lots get rejected

Even at very low p, P(d ≥ 1) can be substantial, so good lots are rejected frequently.

Question 8 · medium

Why is a gauge R&R study done before a capability or charting study?

  1. It estimates the AOQL
  2. It replaces the control chart
  3. Gauge error misleads
  4. It sets the specification limits
Answer and working

C. Gauge error misleads

Observed variation = process + measurement variation; if the gauge contributes much, charts and indices mislead.

Question 9 · medium

Which tool in the Define and Analyse phases ranks defect types by frequency to focus effort?

  1. An OC curve
  2. An EWMA chart
  3. A Pareto chart
  4. A dendrogram
Answer and working

C. A Pareto chart

Pareto analysis shows that a few defect types usually account for most losses.

Question 10 · medium

What is the weak point of accelerated life testing?

  1. It cannot be censored
  2. It needs no failures to occur
  3. Extrapolation to normal use
  4. It ignores temperature
Answer and working

C. Extrapolation to normal use

The stress-life model (e.g. Arrhenius) must hold over the extrapolation range, which is hard to verify.

A study plan for Statistical Quality Control & Reliability in ASRB NET

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (57% of the 35 questions): Process capability indices (6, 17%); Six Sigma and design for quality (introduction) (6, 17%); Chance and assignable causes of variation (4, 11%); Control charts for attributes: p, np, c and u charts (4, 11%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Acceptance sampling by attributes: single, double and sequential plans (3, 9%); Acceptance sampling by variables (3, 9%); CUSUM and EWMA charts (3, 9%); Control charts for variables: X-bar, R and s charts (2, 6%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: OC, AOQ, AOQL, ASN and ATI curves (2, 6%); Reliability: hazard rate, series and parallel systems, life testing (2, 6%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: OC, AOQ, AOQL, ASN and ATI curves (2 hard of 2), Control charts for attributes: p, np, c and u charts (2 hard of 4), Acceptance sampling by attributes: single, double and sequential plans (1 hard of 3).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Process capability indices (1 easy of 6); Six Sigma and design for quality (introduction) (1 easy of 6).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ASRB NET Statistical Quality Control & Reliability

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.