LAISHA
Open Laisha

Tamil Nadu PSC Water Resources Management, Floods & Canal Systems: practice questions

Tamil Nadu PSC — Agricultural Engineering (Code 164, degree standard) · India · Tamil Nadu Public Service Commission

Original practice questions written to the published syllabus · not past papers
10worked here, free
43written to this exam in this subject
9syllabus units

About Tamil Nadu PSC

Tamil Nadu PSC — Agricultural Engineering (Code 164, degree standard) is a government recruitment exam run by Tamil Nadu Public Service Commission, for candidates in India. Degree-standard subject paper (for posts such as Assistant Engineer (Agri)).

Source: tnpsc.gov.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Water Resources Management, Floods & Canal Systems in Tamil Nadu PSC

Managing water at the scale of reservoirs, canals and river basins, including floods and farmer participation.

Our 43 Tamil Nadu PSC questions in this subject: 25 easy, 12 medium, 6 hard, across 9 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Tamil Nadu PSC and are not shown on any other exam's page.

Question 1 · medium

Contours 5 m apart enclose 2.0 km² and 3.2 km² of a reservoir basin. Using the cone (prismoidal) formula, what is the storage between them?

  1. 12.88 Mm³
  2. 13.00 Mm³
  3. 26.00 Mm³
  4. 6.44 Mm³
Answer and working

A. 12.88 Mm³

Cone formula: ΔV = (h/3)(A1 + A2 + √(A1A2)) = (5/3)(2.0 + 3.2 + 2.53) × 10⁶ = 12.88 Mm³. 13.00 is the trapezoidal formula, which slightly overestimates; 26.00 forgets to divide by 2 in the trapezoidal formula; 6.44 halves the right answer.

Question 2 · easy

How does a barrage differ from a weir?

  1. A barrage is built only on rock foundations, whereas a weir is built only on alluvium
  2. A barrage stores water for the whole dry season, whereas a weir only diverts the flood flows
  3. A barrage has a low crest and controls the pond level with gates across its whole length
  4. A barrage has a high solid crest that raises water without any gates or shutters
Answer and working

C. A barrage has a low crest and controls the pond level with gates across its whole length

A weir raises water with a fixed crest (sometimes with small shutters); a barrage has a low crest and gates over the full width, giving better control and less afflux. Neither is a storage dam, and both are common on alluvium.

Question 3 · easy

What do guide banks at a weir or barrage do?

  1. They hold back the pond upstream so that it does not spill over the crest
  2. They confine the river to the waterway of the structure and guide flow through it
  3. They trap sediment upstream of the weir so that the canal receives clear water
  4. They divert part of the river flow into the canal head during the low-flow season
Answer and working

B. They confine the river to the waterway of the structure and guide flow through it

Guide banks (Bell's bunds) train the river through the structure and protect its flanks from outflanking. Diverting flow is the head regulator's job; holding back the pond is the weir's.

Question 4 · hard

Why do designers prefer proportional or slightly sub-proportional outlets near the tail of a distributary?

  1. So that the water level in each watercourse downstream controls the discharge entering every field channel
  2. So that farmers can adjust their own outlets freely without causing any change in the distributary flow
  3. So that when the distributary runs low, head outlets do not take more than their share and starve the tail
  4. So that tail outlets receive their full discharge even while the distributary is closed for maintenance work
Answer and working

C. So that when the distributary runs low, head outlets do not take more than their share and starve the tail

Fair sharing of fluctuations protects the tail. A hyper-proportional outlet upstream takes extra when levels rise and the effect cascades. No outlet delivers when the channel is closed; downstream control would make the outlet non-modular.

Question 5 · easy

Under warabandi, how is each farmer's turn on a watercourse fixed?

  1. Equal hours for every farmer on the watercourse, whatever the size of each holding
  2. Whenever the farmer applies, in the order in which applications are received at the canal office
  3. A fixed time on a fixed day of a weekly cycle, in proportion to the farmer's landholding
  4. A fixed volume per hectare measured at the field inlet, however long the delivery takes
Answer and working

C. A fixed time on a fixed day of a weekly cycle, in proportion to the farmer's landholding

Warabandi gives the whole outlet flow for a time proportional to area, at a fixed day and hour in a 7-day cycle. Application-based allotment is closer to Maharashtra's shejpali; equal hours ignores holding size.

Question 6 · medium

Using Ryves' formula Q = C·A^(2/3) with C = 6.8 (Q in m³/s, A in km²), what is the peak flood from a 500 km² catchment?

  1. About 152 m³/s
  2. About 719 m³/s
  3. About 3,400 m³/s
  4. About 428 m³/s
Answer and working

D. About 428 m³/s

Q = 6.8 × 500^(2/3) = 6.8 × 63.0 = 428 m³/s. 719 uses Dickens' exponent 3/4; 3,400 uses A to the power 1; 152 uses A^0.5.

Question 7 · easy

Which measure reduces flood damage to a house without changing the flood itself?

  1. Raising the plinth above the expected flood level
  2. Widening and deepening the river channel nearby
  3. Raising the crest of the levee along the river
  4. Building a detention basin on a tributary upstream
Answer and working

A. Raising the plinth above the expected flood level

Flood proofing, such as raising plinths, protects property against a given flood. Detention, channel widening and levees all change the flood flow or level.

Question 8 · easy

Under India's classification by culturable command area, a scheme with a CCA of 1,500 ha is

  1. a medium irrigation project
  2. a major irrigation project
  3. a minor irrigation project
  4. a command area development project
Answer and working

C. a minor irrigation project

India: minor below 2,000 ha CCA, medium 2,000–10,000 ha, major above 10,000 ha. Command area development is a programme, not a size class.

Question 9 · hard

A tank's 15 km² catchment receives 900 mm of rain, with a runoff coefficient of 0.25. After 30% losses to evaporation and seepage, the crops need a delta of 0.5 m. About how much area can be irrigated?

  1. About 330 ha
  2. About 1,890 ha
  3. About 675 ha
  4. About 470 ha
Answer and working

D. About 470 ha

Yield = 15 × 10⁶ × 0.9 × 0.25 = 3.375 Mm³; usable = 3.375 × 0.7 = 2.36 Mm³; area = 2.36 × 10⁶ ÷ 0.5 = 4.73 × 10⁶ m² ≈ 473 ha. 675 ignores losses; 1,890 omits the runoff coefficient; 330 applies the loss twice.

Question 10 · easy

What is the function of the sluice in an irrigation tank?

  1. To bring water into the tank from the catchment or upper tank
  2. To release controlled amounts of stored water to the command
  3. To drain the foreshore so that it can be cultivated after the rains
  4. To pass flood water safely when the tank is full to its crest
Answer and working

B. To release controlled amounts of stored water to the command

The sluice is the controlled outlet to the command. Flood passing is the surplus weir; supply is the supply channel.

A study plan for Water Resources Management, Floods & Canal Systems in Tamil Nadu PSC

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (60% of the 43 questions): Diversion works (12, 28%); Canal operation (8, 19%); Reservoirs (6, 14%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Minor irrigation (5, 12%); Flood estimation (3, 7%); Water resources of a country (3, 7%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Water users' associations and participatory irrigation management (3, 7%); Flood control measures (2, 5%); Water quality management (1, 2%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Canal operation (2 hard of 8), Minor irrigation (1 hard of 5), Diversion works (2 hard of 12).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Flood control measures (2 easy of 2); Water quality management (1 easy of 1).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Tamil Nadu PSC Water Resources Management, Floods & Canal Systems

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.