ICAR AICE-JRF/SRF Water Resources Management, Floods & Canal Systems: practice questions

ICAR AICE-JRF/SRF (PhD) — Agricultural Engineering subjects 38–43 · India · National Testing Agency for ICAR

Original practice questions written to the published syllabus · not past papers
10worked here, free
106written to this exam in this subject
9syllabus units

About ICAR AICE-JRF/SRF

ICAR AICE-JRF/SRF (PhD) — Agricultural Engineering subjects 38–43 is a PhD, fellowship and lectureship exam run by National Testing Agency for ICAR, for candidates in India. LAN-based computer test, 2 hours, 120 MCQs: 20 Part A (general knowledge and reasoning), 50 Part B (core group), 50 Part C (specialisation); four options.

Source: icar.org.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Water Resources Management, Floods & Canal Systems in ICAR AICE-JRF/SRF

Water resources planning and management at PG depth: reservoir storage zones and mass-curve sizing, sedimentation and trap efficiency, design flood estimation and frequency analysis, flood control measures, minor irrigation, PIM and water users' associations, water quality.

Managing water at the scale of reservoirs, canals and river basins, including floods and farmer participation.

Our 106 ICAR AICE-JRF/SRF questions in this subject: 17 easy, 56 medium, 33 hard, across 9 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ICAR AICE-JRF/SRF and are not shown on any other exam's page.

Question 1 · medium

A project costs 500 million currency units, has a 50-year life, annual operation and maintenance of 10 million and annual benefits of 60 million. At 8% interest, using the capital recovery factor, what is the benefit-cost ratio?

  1. 3.00
  2. 0.12
  3. 1.18
  4. 1.47
Answer and working

C. 1.18

CRF = 0.08 × 1.08⁵⁰ ÷ (1.08⁵⁰ − 1) = 0.0817. Annual capital cost = 500 × 0.0817 = 40.9; total annual cost = 40.9 + 10 = 50.9; BCR = 60 ÷ 50.9 = 1.18. 3.00 ignores interest (500/50 + 10 = 20); 1.47 leaves out O&M (60 ÷ 40.9); 0.12 divides benefits by the full capital cost.

Question 2 · hard

A catchment of 800 km² yields 1,200 t/km² of sediment a year to a reservoir with 95% trap efficiency. The deposit's dry bulk density is 1.2 t/m³. What volume of sediment is deposited each year?

  1. 0.91 Mm³
  2. 0.76 Mm³
  3. 1.09 Mm³
  4. 0.80 Mm³
Answer and working

B. 0.76 Mm³

Mass trapped = 800 × 1,200 × 0.95 = 912,000 t; volume = 912,000 ÷ 1.2 = 760,000 m³. 0.80 omits trap efficiency; 0.91 forgets to divide by bulk density; 1.09 multiplies by 1.2 instead of dividing.

Question 3 · medium

What is a hedging rule in reservoir operation?

  1. Holding the reservoir at full level throughout the monsoon so that no inflow is ever lost
  2. Releasing the full demand whenever water is available and spilling only when the reservoir is full
  3. Releasing extra water ahead of a forecast flood to create space in the flood cushion
  4. Deliberately releasing less than full demand early in a drought to avoid a larger shortage later
Answer and working

D. Deliberately releasing less than full demand early in a drought to avoid a larger shortage later

Hedging accepts small early shortages to avoid a deep later one. Releasing full demand whenever possible is the standard operating policy; releasing ahead of a forecast flood is pre-release for flood control.

Question 4 · hard

What is valley storage, and why does it matter in assessing a flood-control dam?

  1. The volume the natural channel and flood plain held before the dam; the net gain is reservoir volume minus it
  2. The storage above the maximum water level up to the dam top; it is kept empty as extra flood space at all times
  3. The storage below the outlet sill reserved for sediment; it is excluded from all yield and flood studies alike
  4. The water that seeps into the banks as the reservoir rises; it is added to the flood-control benefit in full
Answer and working

A. The volume the natural channel and flood plain held before the dam; the net gain is reservoir volume minus it

Valley storage existed before the dam, so the flood benefit depends on the net gain. Seepage into banks is bank storage; space above MWL is freeboard; storage below the outlet is dead storage.

Question 5 · hard

A tubewell yields 30 L/s and runs 10 h a day. Peak crop demand is 6 mm/day and application efficiency is 75%. What area can it serve at peak?

  1. 5.4 ha
  2. 13.5 ha
  3. 1.35 ha
  4. 18.0 ha
Answer and working

B. 13.5 ha

Daily volume = 0.030 × 36,000 = 1,080 m³; effective = 810 m³; area = 810 ÷ 0.006 = 135,000 m² = 13.5 ha. 18.0 ignores efficiency; 5.4 uses 4 h; 1.35 slips a decimal.

Question 6 · medium

Why must tanks in a South Indian or Sri Lankan cascade be rehabilitated as a group rather than one at a time?

  1. All tanks in a cascade share a single sluice, so one cannot be repaired without closing all of the others
  2. Cascade tanks are always owned by one landholder, so a single legal approval covers all the tanks together
  3. Tanks in a cascade have no catchment of their own and depend entirely on supply from a canal system
  4. Each tank's surplus and drainage feed the next tank down the valley, so upstream changes alter supply downstream
Answer and working

D. Each tank's surplus and drainage feed the next tank down the valley, so upstream changes alter supply downstream

Cascades are hydrologically linked: raising one bund or desilting one tank changes what the next receives and the flood passing down. Each tank has its own sluice and catchment.

Question 7 · easy

What distinguishes irrigation management transfer from participatory irrigation management?

  1. Transfer applies only to groundwater schemes and tubewells; participation applies only to canal systems
  2. Transfer hands management of part or all of a system to users; participation involves them alongside the agency
  3. Transfer gives users ownership of the dam and headworks; participation gives them only the main canal
  4. Transfer means users pay the agency a higher fee each season; participation means they pay no fee at all
Answer and working

B. Transfer hands management of part or all of a system to users; participation involves them alongside the agency

PIM involves users in planning, operation, maintenance and finance; IMT shifts responsibility (sometimes ownership) to user organisations, usually below a stated level. Neither is defined by fee level or water source.

Question 8 · medium

Which Indian state passed the Farmers' Management of Irrigation Systems Act in 1997, an early state law creating water users' associations?

  1. Himachal Pradesh
  2. Andhra Pradesh
  3. Punjab
  4. Rajasthan
Answer and working

B. Andhra Pradesh

Andhra Pradesh's 1997 Act created WUAs across its irrigation commands and was followed by other states' laws. The other states passed their own laws at different times.

Question 9 · medium

Which is one of Elinor Ostrom's design principles for long-lived common-pool resource institutions such as irrigation systems?

  1. Fixed rules set nationally and applied identically to every system
  2. Management only by a government agency without user involvement
  3. Graduated sanctions for members who break the rules
  4. Equal water shares for all members regardless of their contributions
Answer and working

C. Graduated sanctions for members who break the rules

Ostrom's principles include clear boundaries, rules suited to local conditions with benefits proportional to contributions, collective choice, monitoring, graduated sanctions, conflict resolution, recognition of rights to organise, and nesting. Equal shares regardless of contribution and uniform national rules contradict them.

Question 10 · medium

Which country transferred the management of its irrigation districts to water user associations on a large scale from about 1989?

  1. Japan
  2. Egypt
  3. Australia
  4. Mexico
Answer and working

D. Mexico

Mexico's transfer programme, from about 1989, handed irrigation districts to user associations and is widely studied. Japan has long-established land improvement districts; Egypt and Australia followed different paths.

A study plan for Water Resources Management, Floods & Canal Systems in ICAR AICE-JRF/SRF

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (45% of the 106 questions): Flood estimation (18, 17%); Reservoirs (15, 14%); Water quality management (15, 14%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Flood control measures (12, 11%); Water resources of a country (11, 10%); Canal operation (10, 9%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Diversion works (9, 8%); Water users' associations and participatory irrigation management (9, 8%); Minor irrigation (7, 7%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Canal operation (5 hard of 10), Reservoirs (7 hard of 15), Diversion works (4 hard of 9).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Water resources of a country (3 easy of 11); Water quality management (4 easy of 15).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ICAR AICE-JRF/SRF Water Resources Management, Floods & Canal Systems

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.