LAISHA
Open Laisha

Rajasthan PSC Water Resources Management, Floods & Canal Systems: practice questions

Rajasthan PSC — Assistant Agriculture Engineer (Agriculture Engineering syllabus) · India · Rajasthan Public Service Commission

Original practice questions written to the published syllabus · not past papers
10worked here, free
28written to this exam in this subject
9syllabus units

About Rajasthan PSC

Rajasthan PSC — Assistant Agriculture Engineer (Agriculture Engineering syllabus) is a government recruitment exam run by Rajasthan Public Service Commission, for candidates in India. Objective paper; the paper structure was not captured.

Source: rpsc.rajasthan.gov.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Water Resources Management, Floods & Canal Systems in Rajasthan PSC

Managing water at the scale of reservoirs, canals and river basins, including floods and farmer participation.

Our 28 Rajasthan PSC questions in this subject: 22 easy, 5 medium, 1 hard, across 9 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Rajasthan PSC and are not shown on any other exam's page.

Question 1 · medium

As long quoted by India's Central Water Commission, India's utilisable water resource of 1,122 BCM splits into which components?

  1. 433 BCM surface water and 690 BCM replenishable groundwater
  2. 561 BCM surface water and 561 BCM replenishable groundwater
  3. 690 BCM surface water and 433 BCM replenishable groundwater
  4. 1,869 BCM surface water less 747 BCM evaporation from reservoirs
Answer and working

C. 690 BCM surface water and 433 BCM replenishable groundwater

CWC gives 690 BCM utilisable surface water and 433 BCM replenishable groundwater (1,122 BCM). Swapping the two figures is the usual slip; 1,869 BCM is the average annual resource, not a surface-water component.

Question 2 · easy

Which spillway type carries water down a vertical shaft and through a tunnel, and suits sites with no room for a surface channel?

  1. Side-channel spillway
  2. Chute spillway
  3. Shaft spillway
  4. Ogee (overflow) spillway
Answer and working

C. Shaft spillway

A shaft spillway has a funnel-shaped crest leading to a vertical shaft and tunnel. The ogee crest is an overflow profile on concrete dams; side-channel and chute spillways are open channels.

Question 3 · easy

At a diversion headwork, what is the function of the undersluices?

  1. To measure the discharge entering the canal for seasonal water accounting
  2. To pass fish upstream past the weir during their breeding migration season
  3. To keep a clear, deep approach to the canal head and flush silt deposited in the pocket
  4. To dissipate the energy of the hydraulic jump formed below the weir crest
Answer and working

C. To keep a clear, deep approach to the canal head and flush silt deposited in the pocket

Undersluices (scouring sluices) in the pocket beside the canal head scour deposited silt and maintain a clear channel. Fish passage is the fish ladder's job; measurement and energy dissipation are handled by other works.

Question 4 · medium

Where are the silt excluder and the silt ejector placed in a canal headwork, respectively?

  1. Excluder on the downstream glacis of the weir; ejector in the stilling basin
  2. Excluder a short way down the canal; ejector in the pocket floor upstream of the head regulator
  3. Both in the river upstream of the weir, at the tip of the guide banks
  4. Excluder in the pocket floor upstream of the head regulator; ejector a short way down the canal
Answer and working

D. Excluder in the pocket floor upstream of the head regulator; ejector a short way down the canal

The excluder draws off bed-load-rich bottom water in the pocket before it reaches the regulator; the ejector (extractor) removes silt that has entered the canal. Reversing them is the usual error.

Question 5 · easy

What does a cross regulator in a parent canal do?

  1. It releases surplus water from the canal safely into a natural drain or river nearby
  2. It heads up the parent canal so that offtakes can draw their share when the parent runs low
  3. It measures and controls the flow entering an offtaking distributary from the parent canal
  4. It drops the canal bed where the ground slope is steeper than the designed slope of the channel
Answer and working

B. It heads up the parent canal so that offtakes can draw their share when the parent runs low

The cross regulator heads up the parent canal. Releasing surplus is an escape; dropping the bed is a fall; controlling entry to an offtake is the head regulator.

Question 6 · medium

Under warabandi on a 7-day cycle, how many hours does a farmer with 6 ha in a 120 ha outlet command receive, ignoring conveyance-time adjustments?

  1. 1.2 hours
  2. 20.0 hours
  3. 7.0 hours
  4. 8.4 hours
Answer and working

D. 8.4 hours

Turn = 168 h × 6/120 = 8.4 h. 1.2 h uses 24 h instead of 168 h; 7.0 assumes one hour per day; 20.0 divides 120 by 6.

Question 7 · easy

In north-west India and Pakistan, what is osrabandi?

  1. Rotation of turns among farmers on a single watercourse
  2. A fixed fee charged per hectare of crop irrigated in a season
  3. Rotation of supply among distributaries or minors of a canal
  4. Allotment of water against farmers' crop applications each season
Answer and working

C. Rotation of supply among distributaries or minors of a canal

Osrabandi rotates supply among channels; warabandi rotates turns among farmers on a watercourse; application-based allotment is shejpali.

Question 8 · easy

Which of these is a non-structural flood management measure?

  1. Flood embankments
  2. Flood plain zoning
  3. Channel straightening
  4. Detention basins
Answer and working

B. Flood plain zoning

Zoning regulates land use to reduce damage without changing the flood. Embankments, detention basins and channel works physically alter flood flows or levels.

Question 9 · easy

Which part of an irrigation tank safely passes surplus flood water when the tank is full?

  1. The surplus weir
  2. The supply channel
  3. The foreshore
  4. The sluice (outlet)
Answer and working

A. The surplus weir

The surplus weir passes floods over a fixed crest. The sluice releases water to the command; the supply channel feeds the tank; the foreshore is the area flooded when full.

Question 10 · easy

Which task is normally a function of a water users' association?

  1. Licensing groundwater extraction across the whole of the state
  2. Designing and constructing the main storage dam of the project
  3. Setting national water quality standards for drinking water
  4. Distributing water within its area and maintaining its channels
Answer and working

D. Distributing water within its area and maintaining its channels

WUAs prepare operation plans, distribute water, maintain channels, collect fees and settle disputes within their area. Dams, national standards and state licensing belong to agencies and regulators.

A study plan for Water Resources Management, Floods & Canal Systems in Rajasthan PSC

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (54% of the 28 questions): Canal operation (5, 18%); Diversion works (5, 18%); Minor irrigation (5, 18%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Reservoirs (3, 11%); Water resources of a country (3, 11%); Water users' associations and participatory irrigation management (3, 11%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Flood control measures (2, 7%); Flood estimation (1, 4%); Water quality management (1, 4%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Minor irrigation (1 hard of 5).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Flood control measures (2 easy of 2); Flood estimation (1 easy of 1).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Rajasthan PSC Water Resources Management, Floods & Canal Systems

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files