Rajasthan PSC Soil & Water Conservation Engineering: practice questions

Rajasthan PSC — Assistant Agriculture Engineer (Agriculture Engineering syllabus) · India · Rajasthan Public Service Commission

Original practice questions written to the published syllabus · not past papers
10worked here, free
30written to this exam in this subject
10syllabus units

About Rajasthan PSC

Rajasthan PSC — Assistant Agriculture Engineer (Agriculture Engineering syllabus) is a government recruitment exam run by Rajasthan Public Service Commission, for candidates in India. Objective paper; the paper structure was not captured.

Source: rpsc.rajasthan.gov.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Soil & Water Conservation Engineering in Rajasthan PSC

Estimating erosion and designing the bunds, terraces, waterways, spillways, ponds and dams that control it.

Our 30 Rajasthan PSC questions in this subject: 14 easy, 11 medium, 5 hard, across 10 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Rajasthan PSC and are not shown on any other exam's page.

Question 1 · hard

Contour bunds 0.6 m high with a 0.5 m top width and side slopes of 1.5:1 are laid at a horizontal interval of 20 m on a uniform slope. The earthwork per hectare is closest to:

  1. 150 m³
  2. 690 m³
  3. 16.8 m³
  4. 420 m³
Answer and working

D. 420 m³

Cross-section = H(b + zH) = 0.6 × (0.5 + 1.5 × 0.6) = 0.84 m². Bund length per hectare = 10,000/20 = 500 m. Earthwork = 0.84 × 500 = 420 m³. Using the base width instead of the mean width gives 690; using the top width alone gives 150. 16.8 m³ multiplies the section by the 20 m interval instead of the bund length.

Question 2 · medium

For contour bunds of base width 2.3 m laid at 20 m horizontal interval, the percentage of land occupied by bunds is about:

  1. 2.3%
  2. 11.5%
  3. 10.3%
  4. 2.5%
Answer and working

B. 11.5%

Land under bunds = base width / horizontal interval = 2.3/20 = 11.5%. Using the top width (0.5 m) underestimates the loss at 2.5%. 10.3% divides by the interval plus the base width (2.3/22.3).

Question 3 · easy

Level bench terraces with vertical risers are to be built on a 20% slope with a bench width of 6 m. The vertical interval is:

  1. 1.5 m
  2. 1.2 m
  3. 120 m
  4. 0.3 m
Answer and working

B. 1.2 m

VI = S W / 100 = 20 × 6/100 = 1.2 m. The formula with riser slope, SW/(100 − SU), is needed only when the riser is sloped. Using a riser slope of 1:1 gives 1.5 m, forgetting the /100 gives 120 m, and W/S gives 0.3 m.

Question 4 · medium

Every temporary check dam in a gully should have a spillway notch at its centre mainly to:

  1. reduce the weight of the structure
  2. keep overflow away from the banks, where it would cut around the dam
  3. let fish pass upstream
  4. allow sediment to flush through
Answer and working

B. keep overflow away from the banks, where it would cut around the dam

If water spills at the ends, it scours the gully banks and outflanks the dam. A central notch, an apron below it and keying into bed and banks are standard.

Question 5 · medium

For the principal (normal-flow) outlet of an embankment farm pond, the most commonly used structure is:

  1. a chute spillway down the embankment face
  2. a drop-inlet spillway through or around the embankment
  3. an uncontrolled overflow across the crest
  4. a straight drop spillway on the embankment crest
Answer and working

B. a drop-inlet spillway through or around the embankment

A drop-inlet spillway uses the pond's storage to reduce outflow and passes normal flows safely under the embankment. Floods beyond its capacity go through a vegetated emergency spillway cut in natural ground; overflow across the crest destroys earthen embankments.

Question 6 · medium

A farm pond is to supply two supplementary irrigations of 50 mm (net) each to 2 ha, with an application efficiency of 70%. Ignoring losses, the storage needed for irrigation is closest to:

  1. 1,429 m³
  2. 2,857 m³
  3. 1,400 m³
  4. 2,000 m³
Answer and working

B. 2,857 m³

Net depth total = 2 × 0.05 = 0.10 m; volume net = 20,000 m² × 0.10 = 2,000 m³; gross = 2,000/0.7 = 2,857 m³. Multiplying by efficiency instead of dividing gives 1,400; forgetting the second irrigation gives 1,429.

Question 7 · easy

In the traditional water harvesting of western Rajasthan, a tanka is:

  1. a village pond fed by a natural catchment
  2. a runoff-farming field cropped on stored moisture behind an earthen embankment
  3. an underground cistern filled with runoff from a prepared catchment
  4. a masonry weir across a seasonal stream
Answer and working

C. an underground cistern filled with runoff from a prepared catchment

The tanka is a covered underground tank storing drinking water from a small treated catchment. The runoff-farming field is a khadin; the village pond is a nadi; a masonry weir across a stream is an anicut.

Question 8 · easy

Field shelterbelts give the most protection when oriented:

  1. perpendicular to the direction of the prevailing erosive wind
  2. diagonally at 45° to the wind in every case
  3. along the contour regardless of wind
  4. parallel to the prevailing erosive wind
Answer and working

A. perpendicular to the direction of the prevailing erosive wind

A barrier shelters most area when it faces the erosive wind squarely. Winds that vary in direction reduce effectiveness, and belts are laid out for the dominant erosive direction.

Question 9 · medium

A sandy field begins to blow in a dry spell before any crop is established. An immediate, low-cost control is:

  1. emergency tillage across the wind to bring up clods and form ridges
  2. planting a shelterbelt the same week
  3. irrigating with a sprinkler once the storm has passed
  4. harrowing to smooth and firm the surface
Answer and working

A. emergency tillage across the wind to bring up clods and form ridges

Emergency tillage with a chisel or lister across the wind raises clods and ridges, increasing roughness and the non-erodible fraction immediately. A shelterbelt takes years to grow; smoothing the surface makes erosion worse.

Question 10 · hard

A farmer has planted a single row of dense evergreen trees as a windbreak. Soil still blows in the field beyond about 5 times the tree height, and eddies scour the ground just behind the trees. The best modification is to:

  1. replace the trees with a solid masonry wall of the same height
  2. plant a second identical dense row immediately behind the first so that no wind can pass through the belt
  3. prune the lower branches to let wind pass beneath
  4. convert it to a multi-row belt of moderate porosity, with edge shrubs to close gaps near the ground
Answer and working

D. convert it to a multi-row belt of moderate porosity, with edge shrubs to close gaps near the ground

A very dense barrier creates turbulence and a short sheltered zone. A belt of moderate porosity extends protection downwind, and edge shrubs prevent jetting under the canopy. Pruning the lower branches creates a gap near the ground, and a solid wall worsens the turbulence.

A study plan for Soil & Water Conservation Engineering in Rajasthan PSC

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (70% of the 30 questions): Contour and graded bunds (6, 20%); Farm ponds (6, 20%); Gully control (5, 17%); Wind erosion control and shelterbelts (4, 13%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Bench and broad-base terraces (3, 10%); Drop, drop-inlet and chute spillways (2, 7%); Agronomic and biological conservation measures (1, 3%); Earthen dams: seepage and stability (1, 3%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Mechanics of water erosion (1, 3%); Soil loss estimation: USLE, RUSLE and MUSLE (1, 3%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Farm ponds (2 hard of 6), Bench and broad-base terraces (1 hard of 3), Wind erosion control and shelterbelts (1 hard of 4).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Earthen dams: seepage and stability (1 easy of 1); Mechanics of water erosion (1 easy of 1).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Rajasthan PSC Soil & Water Conservation Engineering

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers