Original practice questions written to the published syllabus · not past papersICAR AICE-JRF/SRF (PhD) — Agricultural Engineering subjects 38–43 is a PhD, fellowship and lectureship exam run by National Testing Agency for ICAR, for candidates in India. LAN-based computer test, 2 hours, 120 MCQs: 20 Part A (general knowledge and reasoning), 50 Part B (core group), 50 Part C (specialisation); four options.
Source: icar.org.in.
Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.
PG-depth understanding: RUSLE and MUSLE factor derivation and limits, sediment delivery and trap efficiency, drop-spillway energy dissipation, earthen dam seepage and stability under drawdown, wind erosion equation factors and shelterbelt design, and the role of remote sensing and GIS in erosion mapping.
Estimating erosion and designing the bunds, terraces, waterways, spillways, ponds and dams that control it.
Our 43 ICAR AICE-JRF/SRF questions in this subject: 2 easy, 21 medium, 20 hard, across 11 units.
Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.
These 10 were written to ICAR AICE-JRF/SRF and are not shown on any other exam's page.
A soil has 60% silt plus very fine sand, 20% clay, 2% organic matter, structure code 2 and permeability class 3. Using 100K = 2.1 M^1.14 (10⁻⁴)(12 − OM) + 3.25(s − 2) + 2.5(p − 3) and the factor 0.1317 to convert to SI, K in t·ha·h/(ha·MJ·mm) is closest to:
C. 0.043
M = (% silt + vfs)(100 − % clay) = 60 × 80 = 4800. 100K = 2.1 × 4800^1.14 × 10⁻⁴ × (12 − 2) = 33.02; the structure and permeability terms are zero. K (US units) = 0.330; × 0.1317 = 0.043 in SI. Forgetting the conversion leaves 0.330; forgetting to divide by 100 gives 4.35; ignoring the clay term in M gives a higher value. Ignoring the clay term (M = 60 × 100 = 6000) gives 0.056.
Which of the following is outside the intended scope of the USLE?
B. Predicting gully erosion from a single large storm
The USLE predicts long-term average annual sheet and rill loss. It was not built for single events or for gully and channel erosion. The other three are its standard planning uses.
A small watershed produces a storm runoff volume of 5,000 m³ with a peak rate of 1.2 m³/s. With K = 0.03, LS = 1.5, C = 0.2 and P = 0.6, MUSLE (Y = 11.8 (Q qp)^0.56 K LS C P) gives a storm sediment yield closest to:
D. 8.3 t
Q·qp = 5000 × 1.2 = 6000; 6000^0.56 = 130.5. Y = 11.8 × 130.5 × 0.03 × 1.5 × 0.2 × 0.6 = 8.3 t. Adding Q and qp (5001.2^0.56) gives 7.5 t, dropping the exponent gives 382 t, and the US-units coefficient 95 with SI inputs gives 67 t.
A small reservoir has 60,000 m³ of dead storage. Sediment inflow is 6,000 t/yr, trap efficiency 85% and deposit dry density 1.2 t/m³. Assuming these stay constant, the dead storage fills in about:
D. 14.1 years
Volume trapped per year = 6000 × 0.85 / 1.2 = 4,250 m³. Life = 60,000 / 4,250 = 14.1 years. Ignoring trap efficiency gives 12.0; ignoring density gives 11.8. In reality trap efficiency falls as the reservoir fills, so life is somewhat longer. 10.2 years multiplies by the trap efficiency instead of dividing (60,000 × 0.85/5,000).
For a parabolic waterway with top width 3.0 m and flow depth 0.6 m, the approximate hydraulic radius R = T²D/(1.5T² + 4D²) is closest to:
A. 0.361 m
R = 3.0² × 0.6/(1.5 × 3.0² + 4 × 0.6²) = 5.40/(13.50 + 1.44) = 0.361 m. Dropping the 4D² term gives (2/3)D = 0.400 m, acceptable only when T is much larger than D; D/2 = 0.300 m is a guess; the rectangular-channel formula bD/(b + 2D) with b = T gives 0.429 m.
For an actively advancing gully with a large runoff-producing catchment above it, the first engineering step is to:
A. divert or control runoff above the gully head and stabilise the head
Gullies advance by head-cutting, so stopping runoff over the head and stabilising it comes first, alongside catchment treatment. Check dams and planting follow once the flow is controlled.
A homogeneous earth dam on an impervious foundation has a horizontal toe filter. The water depth is 8 m, and the horizontal distance from the filter's upstream end to the corrected entry point of the phreatic line is 30 m. With k = 1 × 10⁻⁶ m/s, the seepage per metre length by the Kozeny parabola is closest to:
D. 0.091 m³/day
y0 = √(h² + d²) − d = √(64 + 900) − 30 = 1.048 m. q = k y0 = 10⁻⁶ × 1.048 = 1.048e-06 m³/s per m = 0.091 m³/day per m. Using h instead of y0 overestimates eightfold; forgetting to subtract d gives 2.68. Using h instead of y0 gives 0.691 m³/day.
A dry, cohesionless embankment fill has an angle of internal friction of 32°. For an infinitely long slope of 2.5:1 (horizontal:vertical), the factor of safety against sliding is closest to:
B. 1.56
tan β = 1/2.5 = 0.4. F = tan φ / tan β = 0.6249/0.4 = 1.56. Dividing by 2.5 instead of by 0.4 gives 0.25; using sin φ instead of tan φ gives 1.32; quoting tan φ alone (0.62) ignores the slope.
A horizontal blanket (filter) drain at the downstream base of a homogeneous earth dam is provided chiefly to:
A. keep the phreatic line well inside the downstream slope and lower pore pressures there
The drain draws the seepage line down to its upstream end so it cannot emerge on the downstream face, where it would cause sloughing and piping. It does not stop seepage and has nothing to do with overtopping.
In the Wind Erosion Equation E = f(I, K, C, L, V), the factor L represents:
A. the unsheltered distance across the field along the prevailing erosive wind
I is soil erodibility, K ridge roughness, C the climatic factor, L the unsheltered field length along the wind direction and V vegetative cover. Windbreaks and strip cropping act by reducing L.
This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.
Read the manual chapters for these first and do every worked question you can find on them.
Aim for one sitting per unit, then mixed questions across them.
Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.
Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.
Do these early in revision so they are fast on the day.
Last updated · How Laisha writes and checks its pages · Report a mistake
US$10 a month · one price worldwide · cancel any time
| Free | Smarter | |
|---|---|---|
| Grow guides, pest pages, articles | Read all | Read all |
| Ask Laisha | 5 a day | Up to 1,000 a month |
| Exam practice | The sample on each page | Every question, timed papers |
| Crop calendar and pest alerts | — | For your own fields |
| Calculators and tools | — | All |
| Uploads and reports | — | 100 a month, real files |
An AI operating system for agriculture: free guides, manuals and tools written for every country.