ICAR AICE-JRF/SRF Watershed Planning & Management: practice questions

ICAR AICE-JRF/SRF (PhD) — Agricultural Engineering subjects 38–43 · India · National Testing Agency for ICAR

Original practice questions written to the published syllabus · not past papers
10worked here, free
56written to this exam in this subject
10syllabus units

About ICAR AICE-JRF/SRF

ICAR AICE-JRF/SRF (PhD) — Agricultural Engineering subjects 38–43 is a PhD, fellowship and lectureship exam run by National Testing Agency for ICAR, for candidates in India. LAN-based computer test, 2 hours, 120 MCQs: 20 Part A (general knowledge and reasoning), 50 Part B (core group), 50 Part C (specialisation); four options.

Source: icar.org.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Watershed Planning & Management in ICAR AICE-JRF/SRF

Unit 6 watershed management at PG depth: prioritisation methods (compound parameter, sediment yield index, multi-criteria), hypsometric analysis, participatory institutions, evaluation design, economic analysis and the Common Guidelines.

Planning a whole watershed: delineating it, classifying its land, budgeting its water and choosing harvesting structures with the people who live there.

Our 56 ICAR AICE-JRF/SRF questions in this subject: 3 easy, 30 medium, 23 hard, across 10 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ICAR AICE-JRF/SRF and are not shown on any other exam's page.

Question 1 · hard

A watershed has minimum elevation 580 m, maximum elevation 1240 m and mean elevation 820 m. Using the elevation-relief ratio to approximate the hypsometric integral, which is correct?

  1. HI ≈ 0.36, indicating a youthful (inequilibrium) stage
  2. HI ≈ 0.66, indicating a youthful (inequilibrium) stage
  3. HI ≈ 0.71, indicating a youthful (inequilibrium) stage
  4. HI ≈ 0.36, within Strahler's mature (equilibrium) range
Answer and working

D. HI ≈ 0.36, within Strahler's mature (equilibrium) range

E = (mean − min) / (max − min) = (820 − 580) / (1240 − 580) = 240/660 = 0.364. Strahler read values above about 0.6 as youthful (inequilibrium), about 0.35–0.6 as mature (equilibrium) and lower values as old (monadnock), so 0.36 is mature. 0.66 (mean ÷ max) is not the hypsometric integral; the interpretation is qualitative and also depends on lithology and tectonics.

Question 2 · hard

A 2,000 ha sub-watershed has three erosion intensity mapping units: 600 ha (weightage 17, delivery ratio 0.9), 900 ha (weightage 14, delivery ratio 0.8) and 500 ha (weightage 11, delivery ratio 0.7). Using SYI = [Σ(Ai × Wi × Di) / Aw] × 100 and the bands very high > 1300, high 1200–1300, medium 1100–1200, low 1000–1100, very low < 1000, the sediment yield index and priority are:

  1. 1,415 — very high
  2. 1,156 — very high
  3. 1,156 — medium
  4. 11.6 — very low
Answer and working

C. 1,156 — medium

Σ(Ai × Wi × Di) = 600×17×0.9 + 900×14×0.8 + 500×11×0.7 = 9,180 + 10,080 + 3,850 = 23,110. SYI = 23,110 / 2,000 × 100 = 1,155.5, which falls in the medium band (1100–1200). Leaving out the delivery ratio gives 1,415 and a false 'very high'; forgetting the factor 100 gives 11.6.

Question 3 · medium

In the USBR land classification, class 5 land is:

  1. land that is permanently unsuitable for irrigated farming because of steep slopes, rock or very shallow soils
  2. land highly suitable for a wide range of irrigated crops with no drainage or reclamation needed
  3. land suitable only for rice
  4. land temporarily classed as non-arable pending further drainage or reclamation studies
Answer and working

D. land temporarily classed as non-arable pending further drainage or reclamation studies

Class 5 is a holding class: its suitability depends on special studies (drainage, reclamation, flood protection) not yet done. Class 6 is the permanently non-arable class; class 1 is the most suitable.

Question 4 · hard

In a nearly closed river basin, where downstream users already use most of the flow, an upstream programme builds many new check dams and farm ponds. From a basin water budget perspective, the most likely effect is:

  1. a net increase in basin water supply equal to the storage created
  2. no change to downstream flows because check dams only recharge groundwater, which never reaches the river
  3. a reallocation of water from downstream to upstream users rather than a net creation of new water
  4. a reduction in basin evapotranspiration
Answer and working

C. a reallocation of water from downstream to upstream users rather than a net creation of new water

Harvesting structures capture runoff that would otherwise have flowed downstream; recharged water is then pumped and evapotranspired upstream. In a closed basin this shifts water between users. Storage created is not new supply, and increased irrigation upstream usually raises basin evapotranspiration.

Question 5 · hard

A percolation tank has an average water-spread area of 2.0 ha and an average stored depth of 1.5 m. It fills 3 times in the rainy season, and evaporation takes 20% of the water captured. Assuming all remaining water percolates, the seasonal recharge is:

  1. 90,000 m³
  2. 24,000 m³
  3. 72,000 m³
  4. 18,000 m³
Answer and working

C. 72,000 m³

One filling = 20,000 m² × 1.5 m = 30,000 m³. 3 fillings = 90,000 m³. Recharge = 90,000 × (1 − 0.2) = 72,000 m³. 90,000 m³ ignores evaporation; 24,000 m³ counts only one filling; 18,000 m³ is the evaporation loss.

Question 6 · medium

The jessour of southern Tunisia are best described as:

  1. underground tunnels tapping groundwater from alluvial fans and carrying it by gravity to oasis gardens
  2. roof catchment cisterns for drinking water
  3. pits dug around individual trees on hillslopes
  4. dry-stone or earthen barriers across wadis behind which sediment and runoff build up terraced fields
Answer and working

D. dry-stone or earthen barriers across wadis behind which sediment and runoff build up terraced fields

Jessour are built across wadis; each barrier traps sediment to form a small field that receives runoff from the slopes. Underground tunnels tapping groundwater are qanat or foggara systems; roof cisterns and tree pits are other harvesting types.

Question 7 · hard

In the mass-curve (supply-side) method of sizing a rainwater tank, the required storage is found from:

  1. the maximum difference between the cumulative supply and demand curves during the period when demand exceeds supply
  2. the total annual roof yield
  3. the largest single monthly rainfall
  4. the product of the household's daily demand and the number of rainy days in the wettest year on the rainfall record
Answer and working

A. the maximum difference between the cumulative supply and demand curves during the period when demand exceeds supply

Plotting cumulative roof yield and cumulative demand month by month, the storage needed is the largest gap that must be carried over from surplus months to cover deficit months. Total annual yield sets the upper limit on supply but is not the tank size; the demand-side method uses dry days, not rainy days.

Question 8 · medium

A Venn (chapati) diagram exercise in PRA shows:

  1. the seasonal pattern of rainfall, crop operations and labour demand through the year, month by month
  2. the location of eroded land and gullies
  3. the institutions that matter to villagers and how important and accessible each one is
  4. the cross-section of a check dam
Answer and working

C. the institutions that matter to villagers and how important and accessible each one is

Circles of different sizes represent institutions (importance) and their distance from a central circle representing the community shows accessibility. Seasonal patterns are shown on a seasonal calendar; eroded land on a resource map.

Question 9 · hard

A watershed investment costs 250,000 (currency units) now and yields net benefits of 50,000 per year at the end of each of the next 10 years. At a 10% discount rate, the benefit-cost ratio is about:

  1. 2.00
  2. 1.23
  3. 0.81
  4. 0.77
Answer and working

B. 1.23

Present value factor for an annuity = [1 − (1.10)^−10] / 0.10 = 6.1446. PV of benefits = 50,000 × 6.1446 = 307,228. BCR = 307,228 / 250,000 = 1.23. The undiscounted ratio 2.00 ignores the time value of money; 0.77 discounts the whole sum as if it arrived in year 10. 0.81 is the ratio inverted (250,000/307,228).

Question 10 · medium

China's Sloping Land Conversion Programme ('Grain for Green'), launched in 1999, aimed to:

  1. expand rice cultivation onto steep hillsides
  2. build large hydropower dams in the upper Yangtze to replace hill farming
  3. resettle all hill farmers to cities
  4. pay farmers to convert steep sloping cropland to forest or grassland
Answer and working

D. pay farmers to convert steep sloping cropland to forest or grassland

Grain for Green compensated farmers with grain and cash for converting steep, erodible cropland to trees or grass, to reduce erosion and flooding. It is one of the largest land-use conversion programmes in the world.

A study plan for Watershed Planning & Management in ICAR AICE-JRF/SRF

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (54% of the 56 questions): Watershed characterisation and morphometry (10, 18%); Cost-benefit analysis of watershed projects (8, 14%); Participatory watershed planning (7, 13%); Land capability classification (5, 9%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Land irrigability classification (5, 9%); Rainwater harvesting: check dams, percolation tanks and farm ponds (5, 9%); Watershed delineation (5, 9%); National watershed programmes (4, 7%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Water budgeting (4, 7%); Roof-top rainwater harvesting (3, 5%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Roof-top rainwater harvesting (3 hard of 3), Rainwater harvesting: check dams, percolation tanks and farm ponds (3 hard of 5), Cost-benefit analysis of watershed projects (4 hard of 8).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: National watershed programmes (1 easy of 4); Water budgeting (1 easy of 4).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ICAR AICE-JRF/SRF Watershed Planning & Management

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers