LAISHA
Open Laisha

Tamil Nadu PSC Watershed Planning & Management: practice questions

Tamil Nadu PSC — Agricultural Engineering (Code 164, degree standard) · India · Tamil Nadu Public Service Commission

Original practice questions written to the published syllabus · not past papers
10worked here, free
41written to this exam in this subject
10syllabus units

About Tamil Nadu PSC

Tamil Nadu PSC — Agricultural Engineering (Code 164, degree standard) is a government recruitment exam run by Tamil Nadu Public Service Commission, for candidates in India. Degree-standard subject paper (for posts such as Assistant Engineer (Agri)).

Source: tnpsc.gov.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Watershed Planning & Management in Tamil Nadu PSC

Planning a whole watershed: delineating it, classifying its land, budgeting its water and choosing harvesting structures with the people who live there.

Our 41 Tamil Nadu PSC questions in this subject: 25 easy, 16 medium, 0 hard, across 10 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Tamil Nadu PSC and are not shown on any other exam's page.

Question 1 · easy

A 45 km² watershed contains 63 stream segments of all orders. Its stream frequency is:

  1. 0.71 per km²
  2. 0.14 per km²
  3. 1.40 per km²
  4. 2,835 per km²
Answer and working

C. 1.40 per km²

Stream frequency Fs = ΣN / A = 63 / 45 = 1.40 segments per km². 0.71 inverts the ratio; stream frequency counts segments, not length, so it is not the same as drainage density. 0.14 is a decimal slip in the area (63/450); 2,835 multiplies instead of dividing (63 × 45).

Question 2 · medium

Which item belongs to the socio-economic part of watershed characterisation rather than the physical part?

  1. Drainage density
  2. Soil depth and texture
  3. Land use and land cover map
  4. Landholding size and tenure of households
Answer and working

D. Landholding size and tenure of households

Characterisation has a physical part (relief, soils, drainage, land use, erosion status) and a human part (population, landholding and tenure, cropping and livestock systems, income, institutions). Landholding and tenure decide who benefits and who must agree to treatment, so they are part of the baseline.

Question 3 · medium

On a land capability map, a mapping unit labelled 'IIIe' means:

  1. cultivable land with severe limitations, erosion hazard being the dominant one
  2. non-arable land where erosion is the only limitation
  3. cultivable land with moderate limitations due to excess water
  4. land suitable only for grazing because of shallow soils and a severe erosion hazard
Answer and working

A. cultivable land with severe limitations, erosion hazard being the dominant one

Class III is arable but has severe limitations that reduce the choice of crops or need special conservation practices; the subclass e shows that erosion hazard is the dominant limitation. Moderate limitations define class II, and w would denote wetness.

Question 4 · easy

Which of the following is an agronomic (not a mechanical) soil and water conservation measure on arable land?

  1. Graded bunding
  2. Bench terracing
  3. Strip cropping across the slope
  4. Loose boulder check dams in gullies
Answer and working

C. Strip cropping across the slope

Agronomic measures use crops and cultivation practice: contour cultivation, strip cropping, cover crops, mulching, conservation tillage. Bunds and terraces are mechanical earthworks; loose boulder checks are drainage-line structures.

Question 5 · medium

Staggered contour trenches and half-moon micro-catchments with fodder and tree planting are the typical treatment for:

  1. degraded non-arable upper slopes
  2. level arable land in the valley bottom
  3. drainage lines of fourth and higher order
  4. irrigated land with a high water table
Answer and working

A. degraded non-arable upper slopes

On non-arable land the aim is to re-establish perennial vegetation and to hold runoff close to where it starts; trenches and micro-catchments give seedlings water. Valley arable land is treated with agronomic measures and bunds; larger drainage lines need check dams and nala bunds; waterlogged land needs drainage.

Question 6 · medium

The most important site criterion for a percolation tank, as distinct from a storage tank, is:

  1. permeable, fractured or weathered strata beneath the water spread, linked to an aquifer tapped by wells
  2. an impervious clay bed that holds water through the dry season so that cattle can drink from it
  3. a site as close to the ridge as possible
  4. a deep narrow gorge with solid unfractured rock that stores the largest possible volume per unit of embankment
Answer and working

A. permeable, fractured or weathered strata beneath the water spread, linked to an aquifer tapped by wells

A percolation tank's purpose is groundwater recharge, so the geology under the water spread decides its value. On clay or unfractured rock it stores water but recharges little, and water left standing is lost to evaporation. A narrow gorge suits a storage dam or check dam.

Question 7 · medium

Where roof water is used to recharge groundwater through a recharge pit or borewell, the essential precaution is to:

  1. connect road drains and sewage lines to increase the recharge volume
  2. pass the water through a filter and keep the structure away from septic tanks, soak pits and polluted runoff
  3. build the pit where the water table is within half a metre of the surface, so that recharge reaches it quickly
  4. remove all filter media so the water enters the aquifer faster
Answer and working

B. pass the water through a filter and keep the structure away from septic tanks, soak pits and polluted runoff

Recharge structures deliver water directly to the aquifer, so silt and contaminants must be kept out: filter media (boulders, gravel, sand) and distance from pollution sources are essential. Very shallow water tables leave no room for recharge and increase waterlogging risk.

Question 8 · easy

Which Indian state made roof-top rainwater harvesting compulsory for buildings across the state in the early 2000s?

  1. Punjab
  2. Tamil Nadu
  3. Assam
  4. Himachal Pradesh
Answer and working

B. Tamil Nadu

Tamil Nadu made rainwater harvesting structures compulsory for all buildings across the state in the early 2000s, after severe urban water shortages in Chennai. Many cities in other states have since made harvesting compulsory for new buildings above a set plot size, with rules that differ by city.

Question 9 · easy

In Indian watershed projects, 'entry point activities' are:

  1. small works of immediate, visible benefit to the whole community, done early to build trust
  2. the final hand-over of assets to the panchayat
  3. the construction of the largest check dam first, so that the whole project budget is committed early
  4. the survey of the watershed boundary with a total station before any works or community meetings begin
Answer and working

A. small works of immediate, visible benefit to the whole community, done early to build trust

Entry point activities in the preparatory phase, such as repairing a drinking-water source, show that the project responds to villagers' priorities and build trust before bigger decisions about land and grazing are made. Hand-over happens in the consolidation and withdrawal phase.

Question 10 · medium

Why do most watershed programmes require beneficiaries to contribute part of the cost of works on private land?

  1. It is the main source of finance for the project, covering most of the cost of the engineering works
  2. It allows the agency to exclude poor farmers who cannot pay, so that only commercial farms are treated
  3. It tests genuine demand and builds a fund and a sense of ownership for maintenance after the project
  4. It replaces the need for any technical design
Answer and working

C. It tests genuine demand and builds a fund and a sense of ownership for maintenance after the project

Contribution in cash or labour signals that farmers want the work, and the collected money commonly goes into a watershed development fund for later maintenance. Programmes set lower rates for small and marginal and disadvantaged farmers precisely so the poor are not excluded.

A study plan for Watershed Planning & Management in Tamil Nadu PSC

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (49% of the 41 questions): Land capability classification (6, 15%); National watershed programmes (5, 12%); Roof-top rainwater harvesting (5, 12%); Cost-benefit analysis of watershed projects (4, 10%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Participatory watershed planning (4, 10%); Rainwater harvesting: check dams, percolation tanks and farm ponds (4, 10%); Watershed characterisation and morphometry (4, 10%); Watershed delineation (4, 10%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Water budgeting (3, 7%); Land irrigability classification (2, 5%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Bank the easy marks: Cost-benefit analysis of watershed projects (3 easy of 4); Watershed characterisation and morphometry (3 easy of 4).

    Do these early in revision so they are fast on the day.

  5. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Tamil Nadu PSC Watershed Planning & Management

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.