About Tamil Nadu PSC

Tamil Nadu PSC — Agricultural Engineering (Code 164, degree standard) is a government recruitment exam run by Tamil Nadu Public Service Commission, for candidates in India. Degree-standard subject paper (for posts such as Assistant Engineer (Agri)).

Source: tnpsc.gov.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Surveying & Levelling in Tamil Nadu PSC

Degree-standard recall and computation: chain survey and obstacles, compass and local attraction, plane-table resection, levelling book reduction, contouring for bunds and terraces, land development and levelling design, and total station.

Measuring land, levels and volumes, from chain survey to total station and GNSS, and designing land grading.

Our 86 Tamil Nadu PSC questions in this subject: 42 easy, 39 medium, 5 hard, across 12 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Tamil Nadu PSC and are not shown on any other exam's page.

Question 1 · easy

Which plane-table method is best suited to locating inaccessible points such as the far bank of a river?

  1. Resection
  2. Radiation
  3. Intersection
  4. Traversing
Answer and working

C. Intersection

Intersection fixes a point by rays from two known stations, so no distance to the object is needed. Radiation needs the distance to each point; resection locates the table itself, not the object.

Question 2 · easy

Which accessory is used to centre the plotted point on the plane table exactly over the ground station?

  1. Spirit level
  2. Trough compass
  3. Plumbing fork with plumb bob
  4. Alidade
Answer and working

C. Plumbing fork with plumb bob

The U-fork places a point on the sheet vertically above the ground mark via its plumb bob. The trough compass orients approximately, the alidade sights and draws rays, the spirit level levels the board.

Question 3 · easy

Which of the following is a disadvantage of plane table surveying?

  1. It cannot plot any detail in the field, so all plotting is done in the office
  2. It needs no orientation
  3. It is unsuitable in wet or windy weather and in dense woodland
  4. It requires a detailed field book
Answer and working

C. It is unsuitable in wet or windy weather and in dense woodland

Plane tabling plots in the field, so no field book is needed and errors are seen at once, but the sheet and board are affected by rain and wind, and it needs visibility. It does need orientation at every station.

Question 4 · medium

A contour map has a contour interval of 2 m and the horizontal equivalent between two contours is 50 m. What is the ground slope?

  1. 4% (1 in 25)
  2. 25% (1 in 4)
  3. 2% (1 in 50)
  4. 0.04% (1 in 2500)
Answer and working

A. 4% (1 in 25)

Slope = CI / HE = 2/50 = 0.04 = 4%, i.e. 1 in 25. Inverting gives 25%; 2% divides 1 by 50, ignoring the 2 m interval; 0.04% is the ratio 0.04 written as a percentage without multiplying by 100.

Question 5 · medium

A planimeter with multiplying constant M = 100 cm² is used with the anchor outside the figure. Initial reading 2.162, final reading 7.345, and the zero mark passed the index once in the forward direction. What is the area on the plan?

  1. 481.7 cm²
  2. 1518.3 cm²
  3. 518.3 cm²
  4. 2518.3 cm²
Answer and working

B. 1518.3 cm²

A = M(FR − IR + 10N + C) with C = 0 for anchor outside: 100(7.345 − 2.162 + 10) = 1518.3 cm². Ignoring the disc revolution gives 518.3 cm²; subtracting the readings the wrong way round gives 481.7 cm²; the constant C is used only when the anchor is inside. 2518.3 cm² adds 20 instead of 10 for the zero-mark passage.

Question 6 · easy

A channel in level ground has bed width 4 m and side slopes 1.5 horizontal : 1 vertical. What is the area of cut at a section where the depth is 1.6 m?

  1. 14.08 m²
  2. 10.24 m²
  3. 8.11 m²
  4. 6.40 m²
Answer and working

B. 10.24 m²

A = (b + sh)h = (4 + 1.5 × 1.6) × 1.6 = 10.24 m². The top width is b + 2sh, so the mean width is b + sh; using b + 2sh gives the top-width rectangle (14.08 m²); inverting the slope ratio gives 8.11 m². 6.40 m² is b × h with the side slopes ignored.

Question 7 · medium

A channel with bed width 4 m and side slopes 1.5:1 (H:V) has centre depths of 1.0, 1.6 and 2.2 m at chainages 30 m apart, ground level across. What is the volume of cut by the trapezoidal (average end area) formula?

  1. 625.2 m³
  2. 954.0 m³
  3. 646.8 m³
  4. 630.6 m³
Answer and working

D. 630.6 m³

Areas: 5.50, 10.24, 16.06 m². V = d[(A1 + A3)/2 + A2] = 30[(5.50 + 16.06)/2 + 10.24] = 630.6 m³. The prismoidal value is 625.2 m³; ignoring the middle section gives 646.8 m³. 954.0 m³ adds all three areas without halving the end sections.

Question 8 · easy

Compared with the prismoidal formula, the trapezoidal (average end area) formula for earthwork generally

  1. overestimates it
  2. underestimates the volume
  3. gives the exact volume
  4. cannot be used with level sections
Answer and working

A. overestimates it

For prismoids whose area varies with the square of depth, the average end area formula gives more than the true volume; the prismoidal correction is subtracted. For level sections the correction is (d/6)s(h1 − h2)².

Question 9 · medium

A contractor bills fill volume for an embankment using the volume of material measured in the borrow pit. Why must the engineer apply a factor before comparing it with the compacted embankment volume?

  1. Only the moisture content changes between borrow pit and embankment; the soil volume stays the same
  2. Borrow volumes are always exactly equal to compacted volumes
  3. Soil volume changes between the undisturbed, loose and compacted states, varying with soil type
  4. The prismoidal correction is different for borrow pits
Answer and working

C. Soil volume changes between the undisturbed, loose and compacted states, varying with soil type

Excavated soil bulks and compacted soil shrinks relative to its in-place state, so equal volumes are not equal quantities of earth. Shrinkage and swell factors vary with soil and compaction and are taken from tests or local data.

Question 10 · medium

When the backsight and foresight distances from a level are made equal, which errors cancel in the difference of level?

  1. Staff not held vertical
  2. Settlement of the tripod between readings
  3. Collimation error and the combined curvature-refraction error
  4. Misreading of the staff
Answer and working

C. Collimation error and the combined curvature-refraction error

Equal distances make collimation and curvature-refraction errors identical in both readings, so they cancel in BS − FS. Staff tilt, misreading and tripod settlement are not symmetrical and do not cancel.

A study plan for Surveying & Levelling in Tamil Nadu PSC

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (42% of the 86 questions): Chain and tape surveying, including tape corrections (10, 12%); Compass traversing and bearings (9, 10%); Theodolite traversing and closing error (9, 10%); Contouring (8, 9%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Levelling: rise-and-fall and height-of-instrument methods (8, 9%); Plane table surveying (8, 9%); Earthwork volume computation (7, 8%); Computation of area: trapezoidal and Simpson's rules (6, 7%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Reciprocal levelling (6, 7%); GPS/GNSS surveying (5, 6%); Land grading and levelling design (5, 6%); Total station (5, 6%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Compass traversing and bearings (3 hard of 9), Land grading and levelling design (1 hard of 5), Levelling: rise-and-fall and height-of-instrument methods (1 hard of 8).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: GPS/GNSS surveying (3 easy of 5); Land grading and levelling design (3 easy of 5).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Tamil Nadu PSC Surveying & Levelling

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.