LAISHA
Open Laisha

Tamil Nadu PSC Building Materials, Theory of Structures & Construction: practice questions

Tamil Nadu PSC — Agricultural Engineering (Code 164, degree standard) · India · Tamil Nadu Public Service Commission

Original practice questions written to the published syllabus · not past papers
10worked here, free
41written to this exam in this subject
9syllabus units

About Tamil Nadu PSC

Tamil Nadu PSC — Agricultural Engineering (Code 164, degree standard) is a government recruitment exam run by Tamil Nadu Public Service Commission, for candidates in India. Degree-standard subject paper (for posts such as Assistant Engineer (Agri)).

Source: tnpsc.gov.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Building Materials, Theory of Structures & Construction in Tamil Nadu PSC

Materials, structural members, foundations and estimates for farm buildings and small works.

Our 41 Tamil Nadu PSC questions in this subject: 29 easy, 11 medium, 1 hard, across 9 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Tamil Nadu PSC and are not shown on any other exam's page.

Question 1 · medium

A new brick wall in a farm store develops a white powdery deposit after the first rains. What is it and what causes it?

  1. Carbonation: the burnt clay of the brick reacting with carbon dioxide in the air
  2. Lime bloom: free lime in the cement mortar reacting with nitrogen in the air
  3. Mould growth: fungal spores feeding on organic matter left in the clay bricks
  4. Efflorescence: soluble salts carried to the surface by water that evaporates
Answer and working

D. Efflorescence: soluble salts carried to the surface by water that evaporates

Soluble salts (often sulphates of sodium, potassium or magnesium) in the bricks or mortar dissolve, migrate to the surface and crystallise as the water evaporates. Burnt clay does not carbonate; carbonation is a reaction of calcium hydroxide in cement or lime. Mould is usually dark, not a white crystalline deposit.

Question 2 · easy

A slab panel 3.5 m × 8.0 m is supported on all four edges by beams. How should it be designed?

  1. As a one-way slab spanning the 3.5 m direction, because ly/lx exceeds 2
  2. As a two-way slab, because every slab supported on four edges is two-way
  3. As a one-way slab spanning the 8.0 m direction, because the long span governs
  4. As a flat slab without beams, because the ratio ly/lx is less than 3
Answer and working

A. As a one-way slab spanning the 3.5 m direction, because ly/lx exceeds 2

ly/lx = 8.0/3.5 = 2.29 > 2, so the slab bends mainly across the short span; main bars run parallel to the 3.5 m span with distribution bars along the long direction. Four-edge support makes it two-way only when ly/lx ≤ 2.

Question 3 · medium

A column carries a service load of 750 kN. Allowing 10% for the footing's self-weight and backfill, what side length of square footing is needed on soil with an allowable bearing pressure of 150 kN/m²?

  1. 2.87 m
  2. 5.50 m
  3. 2.24 m
  4. 2.35 m
Answer and working

D. 2.35 m

Area = 750 × 1.10/150 = 5.50 m²; side = √5.50 = 2.35 m. Ignoring self-weight gives 2.24 m; applying the 1.5 load factor to bearing (which uses service loads) gives 2.87 m; 5.50 is the area, not the side.

Question 4 · easy

When is a raft (mat) foundation usually preferred to individual column footings?

  1. When the water table is very deep and the soil bearing capacity is high
  2. When the building is a light single-storey shed governed only by wind uplift
  3. When the footings would cover more than half the plan area or the soil is weak and variable
  4. When the soil is dense gravel and individual footings would be very small and widely spaced
Answer and working

C. When the footings would cover more than half the plan area or the soil is weak and variable

A raft spreads load over the whole plan, lowering pressure and bridging soft spots to reduce differential settlement. On strong soil with small, widely spaced footings, isolated footings are cheaper.

Question 5 · medium

A farm godown is to be built on expansive black cotton soil. Which foundation approach is commonly used in Indian practice to limit swelling and shrinkage damage?

  1. A timber raft laid on the soil surface so the building moves freely with the clay
  2. Isolated footings on the surface with the floor slab cast directly on the swelling clay
  3. Under-reamed piles anchored below the zone of seasonal moisture change, with a grade beam
  4. Shallow strip footings at 0.3 m depth on a thick layer of the same compacted black cotton soil
Answer and working

C. Under-reamed piles anchored below the zone of seasonal moisture change, with a grade beam

Under-reamed piles have enlarged bulbs that anchor the structure below the active zone, and a grade beam spans between them clear of the clay. Shallow footings in the active zone move with the seasons and crack walls. Practice in other countries uses deeper footings, stiffened rafts or moisture barriers.

Question 6 · medium

How much cement is needed for 0.30 m³ of dry 1:6 cement–sand mortar, taking cement bulk density as 1,440 kg/m³?

  1. 205.7 kg
  2. 61.7 kg
  3. 72.0 kg
  4. 432.0 kg
Answer and working

B. 61.7 kg

Cement = 0.30 × 1/(1 + 6) = 0.0429 m³ × 1,440 = 61.7 kg (about 1.23 bags). Dividing by 6 instead of 7 gives 72.0; 205.7 kg is the cement per m³ of dry mortar, not per 0.30 m³. 432.0 kg forgets the 1/7 cement share (0.30 × 1,440).

Question 7 · easy

A farm office of 150 m² plinth area is to be estimated for administrative approval at a plinth-area rate of 16,000 per m², with 5% added for contingencies. What is the estimate?

  1. 2,400,000
  2. 2,640,000
  3. 2,520,000
  4. 2,280,000
Answer and working

C. 2,520,000

150 × 16,000 = 2,400,000; × 1.05 = 2,520,000. 2,400,000 omits contingencies; 2,280,000 subtracts them; 2,640,000 uses 10%. Contingency percentages are set by local rules.

Question 8 · hard

A slab 6 m × 4 m × 0.12 m is cast in 1:1.5:3 nominal-mix concrete. With a dry-volume factor of 1.54 and cement at 1,440 kg/m³, how many 50 kg bags of cement are needed?

  1. 28.4 bags
  2. 23.2 bags
  3. 15.1 bags
  4. 8.1 bags
Answer and working

B. 23.2 bags

Volume = 6 × 4 × 0.12 = 2.88 m³. Cement per m³ = 1.54/5.5 × 1,440/50 = 8.06 bags; × 2.88 = 23.2 bags. Without the 1.54 factor: 15.1; 8.1 is the per-m³ figure; dividing by 4.5 (leaving out the cement part) gives 28.4.

Question 9 · easy

What distinguishes a detailed specification from a general specification?

  1. It is prepared only after completion to record what was actually built
  2. It gives the total cost of the work and the payment schedule to the contractor
  3. It lists only the class of building and the main materials in a few lines
  4. It describes each item's materials, workmanship, tests and mode of measurement in full
Answer and working

D. It describes each item's materials, workmanship, tests and mode of measurement in full

A general (brief) specification outlines the building as a whole and goes with an approximate estimate; a detailed specification covers every item fully and forms part of the contract. Costs and payments are in the estimate and contract conditions; as-built records are a separate document.

Question 10 · easy

What is the measurement book used for in public works?

  1. Recording the results of cube tests for the quality-control laboratory only
  2. Recording the specifications of each item before the tender is invited
  3. Recording measurements of work done and materials received, as the basis for payments
  4. Recording the names and wages of daily labourers for the contractor's payroll
Answer and working

C. Recording measurements of work done and materials received, as the basis for payments

The measurement book is the original record of quantities measured by the engineer; running and final bills are prepared from it, and auditors check against it. Payroll, specifications and test registers are separate records.

A study plan for Building Materials, Theory of Structures & Construction in Tamil Nadu PSC

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (54% of the 41 questions): Bricks, stone and cement (8, 20%); Estimation, costing and rate analysis (8, 20%); Specifications and contracts (6, 15%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Foundations (5, 12%); Concrete and concrete mix design (4, 10%); Reinforced concrete columns (3, 7%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Steel and timber (3, 7%); Trusses (3, 7%); Reinforced concrete beams and slabs (1, 2%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Estimation, costing and rate analysis (1 hard of 8).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Steel and timber (3 easy of 3); Trusses (3 easy of 3).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Tamil Nadu PSC Building Materials, Theory of Structures & Construction

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.