LAISHA
Open Laisha

NCEES PE Agricultural and Biological Engineering Building Materials, Theory of Structures & Construction: practice questions

NCEES PE Agricultural and Biological Engineering · USA · NCEES (ASABE is the content partner)

Original practice questions written to the published syllabus · not past papers
10worked here, free
23written to this exam in this subject
8syllabus units

About NCEES PE Agricultural and Biological Engineering

NCEES PE Agricultural and Biological Engineering is a licensing and registration exam run by NCEES (ASABE is the content partner), for candidates in USA. Computer-based, 85 questions, 9.5-hour appointment (8.5 hours of exam). Once a year (next: 28 Oct 2026). Closed book with the electronic NCEES handbook and supplied searchable ASABE standards; SI and US customary units.

Source: ncees.org.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Building Materials, Theory of Structures & Construction in NCEES PE Agricultural and Biological Engineering

Applying supplied standards and code formulas: load combinations, beam moment and deflection for purlins and joists, timber and steel member checks, concrete beam and slab capacity, footing sizing from allowable bearing pressure, and structural loads on bins and livestock buildings. Expect multi-step numericals in US customary or SI units.

Materials, structural members, foundations and estimates for farm buildings and small works.

Our 23 NCEES PE Agricultural and Biological Engineering questions in this subject: 3 easy, 7 medium, 13 hard, across 8 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to NCEES PE Agricultural and Biological Engineering and are not shown on any other exam's page.

Question 1 · medium

Under ASTM C150, which type of Portland cement is intended for high sulphate resistance?

  1. Type III
  2. Type I
  3. Type V
  4. Type IV
Answer and working

C. Type V

ASTM C150: Type I general purpose, Type II moderate sulphate resistance, Type III high early strength, Type IV low heat of hydration, Type V high sulphate resistance (low C3A). Indian and European standards name sulphate-resisting cements differently.

Question 2 · hard

Soil tests at the site of a dairy effluent sump show a high sulphate content. Which binder choice is most appropriate for the sump's concrete, subject to the local code?

  1. A lime–sand mortar render over ordinary concrete, because lime neutralises all sulphates
  2. A sulphate-resisting or slag/pozzolana blended cement, with a low water–cement ratio
  3. A rapid-hardening cement, so the concrete gains strength before sulphates can reach it
  4. Ordinary Portland cement with extra C3A, because aluminates bind sulphate into harmless salts
Answer and working

B. A sulphate-resisting or slag/pozzolana blended cement, with a low water–cement ratio

Sulphate attack is driven by reaction of sulphates with C3A hydrates and calcium hydroxide; low-C3A (sulphate-resisting) or slag/pozzolana blended cements, plus low permeability (low w/c, good compaction and curing), resist it. Extra C3A makes attack worse, and rapid-hardening cement is usually high in C3A. Codes set the exact cement type and w/c for each sulphate class, and they differ by country.

Question 3 · hard

Under the ACI 318 rule for f′c ≤ 35 MPa, the required average strength is the larger of f′c + 1.34 s and f′c + 2.33 s − 3.5 (MPa). For f′c = 28 MPa and s = 3.5 MPa, what is it?

  1. 36.2 MPa
  2. 31.5 MPa
  3. 33.8 MPa
  4. 32.7 MPa
Answer and working

D. 32.7 MPa

f′c + 1.34 s = 28 + 4.69 = 32.69; f′c + 2.33 s − 3.5 = 28 + 8.155 − 3.5 = 32.66. The larger is 32.7 MPa. 33.8 applies the Indian 1.65 s rule to an ACI problem; 36.2 forgets the − 3.5 term. 31.5 MPa adds only one standard deviation (28 + 3.5).

Question 4 · medium

Why is bamboo generally unsuitable as a substitute for steel reinforcement in structural concrete?

  1. Its tensile strength is much lower than that of concrete, so it adds nothing in tension
  2. It reacts chemically with cement to produce sulphates that cause expansion of the concrete
  3. It swells and shrinks with moisture, bonds weakly and has a low elastic modulus
  4. It is too heavy, adding more dead load to the member than the steel it would replace
Answer and working

C. It swells and shrinks with moisture, bonds weakly and has a low elastic modulus

Bamboo has high tensile strength (far above concrete's), but moisture movement breaks the bond, cracks the concrete, and the low modulus means large deflections; it is also prone to decay inside concrete. It is light, not heavy, and it does not form sulphates with cement.

Question 5 · easy

What is the minimum longitudinal steel for a 300 × 500 mm RC column under IS 456?

  1. 6000 mm²
  2. 1200 mm²
  3. 1500 mm²
  4. 600 mm²
Answer and working

B. 1200 mm²

IS 456 minimum is 0.8% of gross area: 0.008 × 150,000 = 1200 mm². 1500 mm² is ACI 318's 1% minimum; 6000 mm² is the 4% practical maximum; 600 mm² is half the requirement.

Question 6 · hard

In a 15-year-old dairy shed, the RC columns show rust staining and spalled concrete for about 300 mm above the floor, while the upper parts are sound. What is the most likely cause and the sound repair approach?

  1. Foundation settlement causing crushing at the base; underpin every footing before any surface repair
  2. Overloading of the columns by the roof; strengthen the whole length of each column with steel jackets
  3. Poor curing of the upper concrete; coat the upper columns with a curing compound to stop the spread
  4. Manure and wash water attacking the base; repair, treat the bars, restore cover, add a plinth
Answer and working

D. Manure and wash water attacking the base; repair, treat the bars, restore cover, add a plinth

Damage confined to the wet zone at floor level points to corrosion driven by moisture and aggressive manure and cleaning water, not to overload (which would show cracking along the length or at heads) or settlement (which tilts or cracks walls and beams). Repair: break out unsound concrete, clean or replace bars, reinstate cover with a suitable repair mortar, and add a plinth or protective sleeve and drainage so the zone stays drier.

Question 7 · medium

Roof trusses are spaced 4 m apart with panel points every 1.5 m along the plan. The roof load is 0.9 kN/m² of plan area. What load acts at each internal panel point?

  1. 1.35 kN
  2. 5.40 kN
  3. 2.70 kN
  4. 3.60 kN
Answer and working

B. 5.40 kN

Tributary area per internal panel point = 4 × 1.5 = 6 m²; load = 0.9 × 6 = 5.40 kN. Half of that (2.70 kN) acts at each end panel point. 3.60 kN omits the panel length; 1.35 kN omits the truss spacing.

Question 8 · hard

A light open-sided machinery shed has steel trusses with sheet roofing. Under design wind, the roof suction exceeds the dead load. What must the designer check?

  1. Only the bottom chord in additional tension, because suction stretches the bottom chord further
  2. Force reversal in members and the hold-down of trusses against uplift
  3. Only the gravity case, because wind on a roof always increases the downward load on the trusses
  4. Only the bolts in the sheeting, because uplift on sheeting is never passed to the trusses or columns
Answer and working

B. Force reversal in members and the hold-down of trusses against uplift

Net uplift reverses the sign of member forces: the bottom chord, normally in tension, goes into compression and may buckle over its long unbraced length, and the supports must resist pull-out. Wind can act downward on some roof zones but uplift on light roofs is often critical; sheeting fixings, purlins, trusses, columns and foundations all lie on the uplift load path.

Question 9 · hard

A simply supported parallel-chord truss spans 12 m with a depth of 2 m between chord centrelines. A single 60 kN load acts at the midspan bottom joint. Using the method of sections, what is the force in the bottom chord at midspan?

  1. 45 kN tension
  2. 90 kN tension
  3. 90 kN compression
  4. 180 kN tension
Answer and working

B. 90 kN tension

Reactions = 30 kN each. Cut at midspan and take moments about the top joint above the cut: M = 30 × 6 = 180 kN·m = force × depth, so force = 180/2 = 90 kN. The bottom chord of a simply supported truss under gravity is in tension, so compression is wrong in sign; 180 kN forgets to divide by the depth.

Question 10 · medium

A farmer-producer company wants a working 500-tonne cold store delivered by one firm that will design, build, commission and hand it over. Which procurement route matches this?

  1. A percentage-rate contract on the department's schedule of rates for buildings
  2. A turnkey, EPC or design–build contract with a single point of responsibility
  3. A labour contract in which the company buys all equipment and materials itself
  4. An item-rate contract based on the owner's detailed drawings and bill of quantities
Answer and working

B. A turnkey, EPC or design–build contract with a single point of responsibility

Turnkey/EPC contracts put design, construction and commissioning with one contractor, who hands over a functioning facility; FIDIC's Silver Book is an international example. Item-rate and percentage-rate contracts presume the owner has completed the design.

A study plan for Building Materials, Theory of Structures & Construction in NCEES PE Agricultural and Biological Engineering

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (48% of the 23 questions): Concrete and concrete mix design (4, 17%); Reinforced concrete beams and slabs (4, 17%); Foundations (3, 13%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Steel and timber (3, 13%); Trusses (3, 13%); Bricks, stone and cement (2, 9%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Reinforced concrete columns (2, 9%); Specifications and contracts (2, 9%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Concrete and concrete mix design (3 hard of 4), Reinforced concrete beams and slabs (3 hard of 4), Foundations (2 hard of 3).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Reinforced concrete columns (1 easy of 2); Steel and timber (1 easy of 3).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — NCEES PE Agricultural and Biological Engineering Building Materials, Theory of Structures

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.