NCEES PE Agricultural and Biological Engineering Sprinkler & Micro-Irrigation Systems: practice questions

NCEES PE Agricultural and Biological Engineering · USA · NCEES (ASABE is the content partner)

Original practice questions written to the published syllabus · not past papers
10worked here, free
46written to this exam in this subject
14syllabus units

About NCEES PE Agricultural and Biological Engineering

NCEES PE Agricultural and Biological Engineering is a licensing and registration exam run by NCEES (ASABE is the content partner), for candidates in USA. Computer-based, 85 questions, 9.5-hour appointment (8.5 hours of exam). Once a year (next: 28 Oct 2026). Closed book with the electronic NCEES handbook and supplied searchable ASABE standards; SI and US customary units.

Source: ncees.org.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Sprinkler & Micro-Irrigation Systems in NCEES PE Agricultural and Biological Engineering

Design problems: lateral and main sizing with elevation, inlet pressure, TDH and pump power, pump curves and affinity laws, uniformity targets, economic comparison with annual cost.

Designing and evaluating sprinkler and drip systems, from emitter hydraulics to pump selection.

Our 46 NCEES PE Agricultural and Biological Engineering questions in this subject: 1 easy, 27 medium, 18 hard, across 14 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to NCEES PE Agricultural and Biological Engineering and are not shown on any other exam's page.

Question 1 · hard

Sprinklers each discharge 1.8 m³/h and laterals are 18 m apart. The soil's basic intake rate is 8 mm/h. What is the maximum spacing of sprinklers along the lateral?

  1. 45.0 m
  2. 3.47 m
  3. 12.5 m
  4. 25.0 m
Answer and working

C. 12.5 m

From I = 1000 q / (Sl × Sm) with q in m³/h: Sl = 1000 × 1.8 / (8 × 18) = 12.5 m; in practice the next smaller pipe-length multiple (for example 12 m) is chosen. Using 3600 (the L/s constant) with m³/h gives 45 m; converting 1.8 m³/h to 0.5 L/s and then using 1000 gives 3.47 m. 25.0 m uses half the lateral spacing, 1000 × 1.8/(8 × 9).

Question 2 · hard

Runoff appears only near the outer end of a centre pivot on a loam, although the depth per revolution matches crop need. Which change addresses the cause most directly?

  1. Speed the pivot up while keeping the same nozzles
  2. Spread the application over a wider wetted width (booms or wider-throw heads) or add surface storage by tillage
  3. Raise the pivot-point pressure so that all nozzles throw further by the same amount and the outer end dries faster
  4. Swap the nozzles so the outer spans get less water (under-irrigating them)
Answer and working

B. Spread the application over a wider wetted width (booms or wider-throw heads) or add surface storage by tillage

At the outer end the instantaneous application rate is highest because the same wetted width must deliver the largest discharge. Speeding up reduces depth per pass but not the instantaneous rate; reducing outer discharge under-irrigates the largest area. Widening the wetted pattern or storing surface water attacks the rate problem.

Question 3 · hard

An aluminium lateral (internal diameter 50 mm, Hazen-Williams C = 130) carries 10 sprinklers of 0.5 L/s at 12 m spacing, the first 12 m from the inlet. Using Christiansen's F for m = 1.852, what is the friction loss along the lateral?

  1. 18.49 m
  2. 6.16 m
  3. 7.43 m
  4. 6.48 m
Answer and working

C. 7.43 m

Q = 10 × 0.5 = 5 L/s = 0.005 m³/s; L = 10 × 12 = 120 m. hf(no outlets) = 10.67 × 120 × 0.005^1.852 / (130^1.852 × 0.05^4.87) = 18.49 m. F = 1/2.852 + 1/20 + √0.852/600 = 0.402. hf = 18.49 × 0.402 = 7.43 m. Forgetting F gives 18.49 m; using the many-outlet limit 1/(m+1) = 0.351 gives 6.48 m, which underestimates the loss for only 10 outlets; dividing by 3 is the Darcy limit, not Hazen-Williams.

Question 4 · hard

For a 10 % allowable flow variation, what pressure variation is allowed with emitters of exponent x = 0.2, and what design consequence follows?

  1. About 2 %; laterals must be shorter
  2. About 10 %; same as any emitter
  3. About 41 %; longer laterals or steeper slopes are possible
  4. About 50 %; laterals must be shorter
Answer and working

C. About 41 %; longer laterals or steeper slopes are possible

hvar = 1 − 0.9^(1/0.2) = 1 − 0.9⁵ = 0.410, about 41 %. Low-exponent emitters tolerate much larger pressure variation. The linear estimate qvar/x = 50 % overstates it for a large change; multiplying by x gives 2 %, which reverses the logic.

Question 5 · medium

Emitters have Cv = 0.05, there are 2 emitters per plant, and qmin/qavg in the block is 0.93. What is the design emission uniformity (Keller–Karmeli)?

  1. 88.8 %
  2. 87.1 %
  3. 95.5 %
  4. 89.7 %
Answer and working

A. 88.8 %

EU = 100 (1 − 1.27 Cv/√n)(qmin/qavg) = 100 (1 − 1.27 × 0.05/1.414) × 0.93 = 100 × 0.9551 × 0.93 = 88.8 %. Omitting √n gives 87.1 %; omitting qmin/qavg gives 95.5 %; omitting 1.27 gives 89.7 %.

Question 6 · hard

A grower chlorinates drip water from a well with pH 8.3 to control bacterial slime, but results are poor. Which change most improves chlorine's effectiveness?

  1. Raise pH further with an alkali
  2. Mix the chlorine into the fertiliser stock solution so both are injected together
  3. Inject chlorine only after the filter backflush
  4. Inject acid to lower pH, since hypochlorous acid predominates at lower pH
Answer and working

D. Inject acid to lower pH, since hypochlorous acid predominates at lower pH

Chlorine in water is present as hypochlorous acid (a strong biocide) and hypochlorite ion (weak); the balance shifts towards hypochlorous acid as pH falls, so acid improves effectiveness. Mixing chlorine with fertilisers can cause reactions and is avoided.

Question 7 · medium

All emitters on a farm together would draw 100 m³/h, but the pump and source supply 30 m³/h. The required run time is 2.2 h per day. How many shifts are needed, and what daily operating time results?

  1. 3 shifts; about 6.6 h/day
  2. 4 shifts; about 8.8 h/day
  3. 4 shifts; about 2.2 h/day
  4. 30 shifts; about 66 h/day
Answer and working

B. 4 shifts; about 8.8 h/day

100/30 = 3.33, rounded up to 4 shifts (3 shifts would each need 33 m³/h, more than the source). Daily time = 4 × 2.2 = 8.8 h, which must fit within available pumping hours. The run time per shift does not change with the number of shifts.

Question 8 · medium

How is the operating point of a centrifugal pump in an irrigation system found?

  1. At the intersection of the pump head–flow curve and the system head curve
  2. At the pump's best-efficiency point, whatever the system head curve happens to be
  3. At the shut-off head
  4. At the maximum flow shown on the pump curve
Answer and working

A. At the intersection of the pump head–flow curve and the system head curve

The pump delivers the flow at which the head it produces equals the head the system requires. The designer then checks that this point is close to best efficiency; if it is not, the pump or impeller is changed.

Question 9 · hard

A pump installed with a high suction lift makes a crackling noise and its impeller shows pitting. Which condition explains this?

  1. The system curve is too flat
  2. The delivery pipe is oversized
  3. NPSH available is too low
  4. The pump runs at its best-efficiency point, which always produces some impeller cavitation
Answer and working

C. NPSH available is too low

Cavitation occurs when NPSH available falls below NPSH required: vapour bubbles form in the eye of the impeller and collapse, causing noise and pitting. Remedies include reducing suction lift or suction losses.

Question 10 · hard

In an automatic filter station, what sensor normally starts the backflush sequence (besides a backup timer)?

  1. A soil moisture sensor
  2. A water-level float in the source
  3. A rain sensor
  4. A differential pressure switch across the filters
Answer and working

D. A differential pressure switch across the filters

The differential pressure switch detects the rise in head loss as the filter loads and triggers backflush at the set value; a timer provides a backup. The other sensors control irrigation, not filter cleaning.

A study plan for Sprinkler & Micro-Irrigation Systems in NCEES PE Agricultural and Biological Engineering

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (50% of the 46 questions): System layout and pump selection (6, 13%); Drip lateral and sub-main design (5, 11%); Christiansen's uniformity coefficient (4, 9%); Emission uniformity (4, 9%); Sprinkler lateral and main design (4, 9%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Allowable pressure variation and the friction factor F (3, 7%); Economics of pressurised irrigation (3, 7%); Emitter hydraulics: exponent and coefficient of variation (3, 7%); Fertigation (3, 7%); Sprinkler spacing and application rate (3, 7%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Automation (2, 4%); Drip system components (2, 4%); Filtration (2, 4%); Sprinkler types and components (2, 4%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Allowable pressure variation and the friction factor F (2 hard of 3), Emitter hydraulics: exponent and coefficient of variation (2 hard of 3), Sprinkler spacing and application rate (2 hard of 3).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Drip system components (1 easy of 2).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — NCEES PE Agricultural and Biological Engineering Sprinkler & Micro-Irrigation Systems

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers