LAISHA
Open Laisha

ICAR AIEEA-PG Agricultural Drainage Engineering: practice questions

ICAR AIEEA-PG — Agricultural Engineering & Technology (Major Subject Group 10) · India · National Testing Agency for ICAR

Original practice questions written to the published syllabus · not past papers
10worked here, free
57written to this exam in this subject
11syllabus units

About ICAR AIEEA-PG

ICAR AIEEA-PG — Agricultural Engineering & Technology (Major Subject Group 10) is a postgraduate admission exam run by National Testing Agency for ICAR, for candidates in India. Computer-based, 120 minutes, 120 MCQs, +4 / −1, English only (2026 bulletin). One paper for the whole subject group.

Source: icar.org.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Agricultural Drainage Engineering in ICAR AIEEA-PG

Single-answer MCQs on causes and effects of waterlogging, drainage coefficient, surface and subsurface system types, envelope functions, saline-sodic classification limits, amendments and water-quality indices, with short calculations.

Removing excess water and salt: surface and subsurface drain design, and reclaiming saline and sodic land.

Our 57 ICAR AIEEA-PG questions in this subject: 26 easy, 30 medium, 1 hard, across 11 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ICAR AIEEA-PG and are not shown on any other exam's page.

Question 1 · medium

A rainfall of 30 mm percolates to a shallow water table in a soil of drainable porosity 0.06. By how much does the water table rise?

  1. 1.8 mm
  2. 0.50 m
  3. 0.05 m
  4. 5.0 m
Answer and working

B. 0.50 m

Rise = recharge / drainable porosity = 0.030 m / 0.06 = 0.50 m. Multiplying (30 x 0.06 = 1.8 mm) is the common error; 0.05 m and 5 m are decimal slips. Small drainable porosity means a small recharge causes a large rise.

Question 2 · easy

Heavy weed growth in an open drain has which effect?

  1. It raises Manning's n and so lowers the drain's capacity
  2. It lowers Manning's n and so raises capacity
  3. It has no effect on capacity, only on water quality
  4. It increases velocity by narrowing the channel
Answer and working

A. It raises Manning's n and so lowers the drain's capacity

Vegetation adds roughness; with a higher n, Q = (1/n) A R^(2/3) S^(1/2) falls, and water levels rise. That is why maintenance is part of design.

Question 3 · easy

Why did Hooghoudt replace the depth to the impermeable layer D by an equivalent depth d?

  1. To allow for evaporation losses from the water table midway between the drains in dry spells
  2. To account for the extra head loss from radial convergence of flow near a pipe drain
  3. To correct for the drain pipe's roughness
  4. To convert a transient water-table problem into an equivalent steady-state one
Answer and working

B. To account for the extra head loss from radial convergence of flow near a pipe drain

Flow converges radially into a small pipe, which the horizontal-flow (Dupuit-Forchheimer) assumption ignores. Using a smaller d adds the right amount of resistance. It has nothing to do with pipe roughness or time.

Question 4 · easy

How does water enter a corrugated plastic drain pipe?

  1. Through slots cut in the valleys of the corrugations
  2. Through the joints between short pipe sections
  3. By diffusion through the plastic wall
  4. Only through the open upstream end
Answer and working

A. Through slots cut in the valleys of the corrugations

Corrugated pipe is perforated with slots in the valleys. Water entering at the joints describes clay tiles, which were laid as short sections.

Question 5 · easy

An interceptor drain is used to:

  1. Lower a water table fed by uniform rainfall or irrigation recharge over the whole field
  2. Cut off groundwater seeping laterally into an area from higher land or a canal
  3. Remove ponded surface water from depressions
  4. Relieve artesian pressure beneath a clay layer
Answer and working

B. Cut off groundwater seeping laterally into an area from higher land or a canal

Interceptors deal with lateral inflow from outside the area. Water arriving over the area itself is handled by relief (parallel) drains; artesian pressure by relief wells.

Question 6 · medium

A crop's seasonal ETc is 600 mm and the leaching requirement is 0.15. What depth of irrigation water must be applied (no rain, leaching with every irrigation)?

  1. 690 mm
  2. 706 mm
  3. 510 mm
  4. 4000 mm
Answer and working

B. 706 mm

Diw = ETc / (1 - LR) = 600 / 0.85 = 706 mm. 690 mm adds 15 % of ETc (600 x 1.15), which is slightly too little; 510 mm subtracts; 4000 mm divides by LR.

Question 7 · easy

Which description fits a sodic (alkali) soil?

  1. White salt crust, flocculated structure and pH below 8.5
  2. ECe above 4 dS/m with a high gypsum content, flocculated clay and good permeability
  3. ESP above 15, ECe below 4 dS/m, pH 8.5-10, dispersed clay and poor permeability
  4. Acidic pH below 5.5 caused by sulphides
Answer and working

C. ESP above 15, ECe below 4 dS/m, pH 8.5-10, dispersed clay and poor permeability

Sodic soils have dispersed clay and organic matter ('black alkali'), high pH and very low permeability. White crusts mark saline soils; acid sulphate soils are a different problem.

Question 8 · medium

A saline-sodic soil is to be reclaimed. What is the correct sequence?

  1. Leach with good water first to remove salts, then apply gypsum
  2. Apply a calcium amendment such as gypsum first, then leach
  3. Leach only; no amendment is ever needed
  4. Apply lime to raise pH, then leach
Answer and working

B. Apply a calcium amendment such as gypsum first, then leach

If the salts are leached first, the clay disperses and the soil becomes sodic and nearly impermeable. Calcium must replace exchangeable sodium first. Lime is insoluble at high pH and raising pH is the wrong direction.

Question 9 · medium

Soil CEC is 20 meq/100 g. What is the gypsum requirement in meq/100 g to lower ESP from 30 to 10?

  1. 4 meq/100 g
  2. 6 meq/100 g
  3. 2 meq/100 g
  4. 40 meq/100 g
Answer and working

A. 4 meq/100 g

GR = (ESPi - ESPf) x CEC / 100 = 20 x 20 / 100 = 4 meq/100 g. 6 uses the initial ESP only; 2 uses the final ESP; 40 forgets to divide by 100.

Question 10 · easy

Irrigation water has EC 1,500 uS/cm. In the USDA Salinity Laboratory scheme its salinity class is:

  1. C3 (high)
  2. C1 (low)
  3. C2 (medium)
  4. C4 (very high)
Answer and working

A. C3 (high)

C1 < 250, C2 250-750, C3 750-2,250, C4 > 2,250 uS/cm. 1,500 falls in C3.

A study plan for Agricultural Drainage Engineering in ICAR AIEEA-PG

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (47% of the 57 questions): Causes and effects of waterlogging (7, 12%); Reclamation of saline and sodic soils and gypsum requirement (7, 12%); Salinity and the leaching requirement (7, 12%); Drain pipes and envelopes (6, 11%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Drainage coefficient (6, 11%); Irrigation water quality: EC, SAR and RSC (5, 9%); Surface drainage design (5, 9%); Vertical drainage and bio-drainage (5, 9%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Subsurface drain spacing: Hooghoudt and Ernst (4, 7%); Interceptor and relief drains (3, 5%); Kirkham and Glover-Dumm equations (2, 4%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Causes and effects of waterlogging (1 hard of 7).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Interceptor and relief drains (2 easy of 3); Irrigation water quality: EC, SAR and RSC (3 easy of 5).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ICAR AIEEA-PG Agricultural Drainage Engineering

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.