LAISHA
Open Laisha

Agricultural and Biosystems Engineers Licensure Examination Engineering Economics, Project & Business Management: practice questions

Agricultural and Biosystems Engineers Licensure Examination (ABELE) · Philippines · Professional Regulatory Board of Agricultural and Biosystems Engineering, PRC

Original practice questions written to the published syllabus · not past papers
10worked here, free
53written to this exam in this subject
9syllabus units

About Agricultural and Biosystems Engineers Licensure Examination

Agricultural and Biosystems Engineers Licensure Examination (ABELE) is a licensing and registration exam run by Professional Regulatory Board of Agricultural and Biosystems Engineering, PRC, for candidates in Philippines. Paper-based, 2 days (Day 1 6 hours; Day 2 5 hours + 4 hours). Non-programmable calculator only; the Dec 2025 programme bans the Casio fx-991ES/ES Plus by name.

Source: prc.gov.ph.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Engineering Economics, Project & Business Management in Agricultural and Biosystems Engineers Licensure Examination

Project management, machinery cost analysis, depreciation and break-even problems set within the allied-subjects papers, solved with a non-programmable calculator.

Money and time in engineering decisions: discounting, costs, break-even, project appraisal, scheduling and starting a business.

Our 53 Agricultural and Biosystems Engineers Licensure Examination questions in this subject: 19 easy, 25 medium, 9 hard, across 9 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to Agricultural and Biosystems Engineers Licensure Examination and are not shown on any other exam's page.

Question 1 · hard

A grading line costs 240,000 and earns net receipts of 60,000 a year. What is its discounted payback period at 10 % a year, interpolating within the year?

  1. 4.0 years
  2. 5.4 years
  3. 6.0 years
  4. 3.6 years
Answer and working

B. 5.4 years

Cumulative discounted receipts: 60,000(P/A, 10 %, n) reaches 240,000 between year 5 (227,447) and year 6 (261,316); interpolation gives 5.4 years. 4.0 years is simple payback, 240,000/60,000, which ignores interest; discounted payback is always longer. 3.6 years compounds the receipts instead of discounting them (240,000/(60,000 × 1.1)).

Question 2 · medium

A tractor costs 800,000, has a salvage value of 80,000 and a recovery period of 8 years. Using double declining balance, what is the depreciation in year 2?

  1. 150,000
  2. 200,000
  3. 135,000
  4. 90,000
Answer and working

A. 150,000

d = 2/n = 0.25. D1 = 0.25 × 800,000 = 200,000; BV1 = 600,000; D2 = 0.25 × 600,000 = 150,000. 200,000 is year 1; 135,000 wrongly applies the rate to B − S, but declining balance uses book value and ignores salvage until the floor is reached; 90,000 is straight line.

Question 3 · medium

A tractor costs 800,000, has a salvage value of 80,000 and a recovery period of 8 years. Using sum-of-years digits, what is the depreciation in year 3?

  1. 160,000
  2. 120,000
  3. 140,000
  4. 133,333
Answer and working

B. 120,000

SUM = 8 × 9/2 = 36. D3 = (8 − 3 + 1)/36 × (800,000 − 80,000) = 6/36 × 720,000 = 120,000. 160,000 and 140,000 are years 1 and 2; 133,333 applies the fraction to first cost instead of the depreciable amount.

Question 4 · easy

A spice-grinding unit has fixed costs of 600,000 a year, sells at 50 a kg and has variable costs of 30 a kg. What is its break-even output?

  1. 30,000 kg
  2. 12,000 kg
  3. 20,000 kg
  4. 7,500 kg
Answer and working

A. 30,000 kg

Q* = F/(p − v) = 600,000/(50 − 30) = 30,000 kg. 12,000 divides by price and 20,000 by variable cost; 7,500 adds them instead of subtracting. The contribution margin, p − v, is what covers fixed cost.

Question 5 · medium

A spice-grinding unit has fixed costs of 600,000 a year, a price of 50 a kg and variable costs of 30 a kg. If it plans to sell 40,000 kg, what is its margin of safety as a percentage of planned sales?

  1. 25.0 %
  2. 33.3 %
  3. 75.0 %
  4. 20.0 %
Answer and working

A. 25.0 %

Break-even = 600,000/20 = 30,000 kg. Margin of safety = 40,000 − 30,000 = 10,000 kg = 10,000/40,000 = 25.0 % of planned sales. 33.3 % divides by break-even output instead; 75 % is break-even as a share of plan; 20 % is the contribution per kg read as a percentage.

Question 6 · hard

Owning a paddy transplanter costs 150,000 a year in ownership cost plus 900 per hectare to operate. A contractor charges 2,400 per hectare. Above what annual area is owning cheaper than hiring?

  1. 62.5 ha
  2. 166.7 ha
  3. 45.5 ha
  4. 100 ha
Answer and working

D. 100 ha

Set 150,000 + 900A = 2,400A, so A* = 150,000/(2,400 − 900) = 100 ha. Above 100 ha owning is cheaper. 62.5 ha ignores the owner's operating cost; 166.7 ha divides by the operating cost; 45.5 ha adds the two rates.

Question 7 · easy

A feed plant with a capacity of 50,000 t a year breaks even at 30,000 t. What capacity utilisation is needed to break even?

  1. 40 %
  2. 60 %
  3. 167 %
  4. 30 %
Answer and working

B. 60 %

Break-even capacity utilisation = 30,000/50,000 = 60 %. 40 % is the unused share; 167 % inverts the ratio; 30 % confuses tonnes with per cent. Lenders read this figure as a measure of risk: the higher it is, the less room the project has for a poor season.

Question 8 · easy

A pump still works reliably, but a new model uses 30 % less energy for the same duty. The loss in value of the old pump for this reason is called:

  1. Physical depreciation from wear and tear
  2. Sunk cost of the original purchase price
  3. Obsolescence, or functional depreciation
  4. Salvage value at the end of its life
Answer and working

C. Obsolescence, or functional depreciation

Obsolescence is the loss of value caused by better technology or changed requirements, not by wear. Physical depreciation comes from use, corrosion and accidents. It is one of the main reasons assets are replaced before they wear out.

Question 9 · medium

Activities and durations in days, with predecessors: A 4 (none), B 6 (none), C 5 (after A), D 3 (after A), E 4 (after B and D), F 2 (after C and E). What is the project duration?

  1. 24 days
  2. 11 days
  3. 12 days
  4. 13 days
Answer and working

D. 13 days

Forward pass: A 0–4, B 0–6, C 4–9, D 4–7, E starts at max(6, 7) = 7 and ends 11, F starts at max(9, 11) = 11 and ends 13. 24 days adds all durations as if in series; 11 days is path A–C–F and 12 days path B–E–F, both shorter than the critical path A–D–E–F.

Question 10 · easy

The plan-do-check-act cycle of continuous improvement is associated with:

  1. Frederick W. Taylor
  2. W. Edwards Deming
  3. Henri Fayol
  4. Philip Kotler
Answer and working

B. W. Edwards Deming

Deming popularised the PDCA (Shewhart) cycle as the core of quality improvement. Taylor founded scientific management, Fayol set out principles of administration, and Kotler is a marketing author.

A study plan for Engineering Economics, Project & Business Management in Agricultural and Biosystems Engineers Licensure Examination

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (45% of the 53 questions): Break-even analysis (8, 15%); Entrepreneurship and marketing (8, 15%); Fixed and variable costs (8, 15%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: CPM and PERT (6, 11%); Depreciation methods (6, 11%); NPV, IRR, benefit-cost ratio and payback (6, 11%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Time value of money (5, 9%); Replacement analysis (4, 8%); Project appraisal and detailed project reports (2, 4%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: NPV, IRR, benefit-cost ratio and payback (4 hard of 6), Project appraisal and detailed project reports (1 hard of 2), Break-even analysis (2 hard of 8).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Time value of money (3 easy of 5); Entrepreneurship and marketing (4 easy of 8).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — Agricultural and Biosystems Engineers Licensure Examination Engineering Economics, Project

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.