LAISHA
Open Laisha

ICAR AICE-JRF/SRF Engineering Economics, Project & Business Management: practice questions

ICAR AICE-JRF/SRF (PhD) — Agricultural Engineering subjects 38–43 · India · National Testing Agency for ICAR

Original practice questions written to the published syllabus · not past papers
10worked here, free
42written to this exam in this subject
9syllabus units

About ICAR AICE-JRF/SRF

ICAR AICE-JRF/SRF (PhD) — Agricultural Engineering subjects 38–43 is a PhD, fellowship and lectureship exam run by National Testing Agency for ICAR, for candidates in India. LAN-based computer test, 2 hours, 120 MCQs: 20 Part A (general knowledge and reasoning), 50 Part B (core group), 50 Part C (specialisation); four options.

Source: icar.org.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Engineering Economics, Project & Business Management in ICAR AICE-JRF/SRF

Project planning and management for processing plants: DPR structure, financial indicators (NPV, IRR, B/C, payback, break-even capacity, DSCR), CPM and PERT computations, and linear programming formulation and duality.

Money and time in engineering decisions: discounting, costs, break-even, project appraisal, scheduling and starting a business.

Our 42 ICAR AICE-JRF/SRF questions in this subject: 9 easy, 16 medium, 17 hard, across 9 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to ICAR AICE-JRF/SRF and are not shown on any other exam's page.

Question 1 · hard

A processing plant has 500 lamps that fail at random. Replacing a lamp individually after failure costs much more per lamp than replacing all lamps together. Under the standard group-replacement rule, when should all lamps be replaced?

  1. Only once more than half the lamps have failed, because replacing a whole group earlier throws away good lamps
  2. Never, because replacing lamps that still work cannot reduce the total cost of lighting
  3. Every period, because the cost of replacing all lamps together is lower per lamp
  4. At the end of period t if individual replacements in period t + 1 would cost more than the average cost per period up to t
Answer and working

D. At the end of period t if individual replacements in period t + 1 would cost more than the average cost per period up to t

Group replacement trades away the remaining life of working lamps for a lower cost per lamp and fewer emergency replacements. The best interval minimises average cost per period; the rule stated finds that interval. Replacing every period ignores that working lamps are discarded too often.

Question 2 · medium

In the economic (as opposed to financial) analysis of an irrigation project, how is a government subsidy on pump sets treated?

  1. It is added to the project's benefits, because it raises the farmers' net income
  2. It is deducted from the costs and kept, because it is cash the project receives
  3. It is excluded as a transfer, and pump sets are valued at their economic cost
  4. It is counted twice, once as a cost to government and once as a farmer benefit
Answer and working

C. It is excluded as a transfer, and pump sets are valued at their economic cost

Taxes, subsidies and loan transactions move purchasing power between groups without using real resources, so economic analysis removes them and values inputs at their economic or shadow prices. The financial analysis, from the farmer's viewpoint, does include the subsidy.

Question 3 · easy

What is the main purpose of a pre-feasibility study?

  1. To give the final design drawings and tender documents used by contractors to build the project
  2. To evaluate the impact of a completed project several years after it has started
  3. To screen a project idea quickly from secondary data before paying for a full study
  4. To negotiate the loan agreement and repayment schedule with the financing bank
Answer and working

C. To screen a project idea quickly from secondary data before paying for a full study

A pre-feasibility study decides whether an idea deserves the cost of a detailed feasibility study. Detailed design, ex-post evaluation and loan negotiation come at later stages of the project cycle.

Question 4 · medium

A project protected by import duties shows a financial IRR of 18 % but an economic IRR of 6 %. What does this most directly suggest?

  1. That the financial analysis has an arithmetic error, because the two rates must be equal
  2. That the economic analysis is wrong, because it should always give the higher of the rates
  3. That protection makes it pay its owner while it uses resources inefficiently for society
  4. That the project should be financed at 12 %, the average of its financial and economic rates
Answer and working

C. That protection makes it pay its owner while it uses resources inefficiently for society

Financial and economic IRRs differ when market prices differ from economic values. Protection raises the price the owner receives above the border price, inflating financial returns; at border prices the project earns little. Neither rate must exceed the other in general.

Question 5 · hard

Activities and durations in days, with predecessors: A 4 (none), B 6 (none), C 5 (after A), D 3 (after A), E 4 (after B and D), F 2 (after C and E). What is the free float of activity B?

  1. 0 days
  2. 2 days
  3. 1 day
  4. 6 days
Answer and working

C. 1 day

Free float = earliest start of the successor − EF of the activity. B finishes at 6 at the earliest; its successor E cannot start before 7 because of D. Free float = 7 − 6 = 1 day, which here equals its total float. 2 days is C's float; 6 days is B's duration. 0 days assumes B lies on the critical path.

Question 6 · medium

An activity has a normal time of 10 days at a cost of 50,000 and a crash time of 6 days at a cost of 70,000. What is its cost slope?

  1. 5,000 per day
  2. 2,000 per day
  3. 7,000 per day
  4. 11,667 per day
Answer and working

A. 5,000 per day

Cost slope = (crash cost − normal cost)/(normal time − crash time) = (70,000 − 50,000)/(10 − 6) = 5,000 per day. 2,000 divides by the normal time; 7,000 divides the whole crash cost by 10; 11,667 divides crash cost by 6 days.

Question 7 · hard

To shorten a project by one day at least cost, which activity should be crashed first: critical activity P (cost slope 4,000 per day), critical activity Q (2,500 per day), critical activity R (6,000 per day) or non-critical activity S (1,000 per day)?

  1. S, the activity with the lowest cost slope of all
  2. R, the critical activity with the highest cost slope
  3. P, the critical activity with the middle cost slope
  4. Q, the critical activity with the lowest cost slope
Answer and working

D. Q, the critical activity with the lowest cost slope

Only shortening a critical activity reduces project duration; crashing S spends money and saves nothing. Among critical activities, crash the one with the lowest cost slope first, then recompute the critical path because another path may become critical.

Question 8 · hard

The primal LP maximises profit subject to 'less than or equal to' resource constraints with non-negative variables. Its dual is:

  1. A minimisation with 'greater than or equal to' constraints and the same optimal value
  2. A maximisation with 'less than or equal to' constraints and the same objective coefficients
  3. A minimisation with 'less than or equal to' constraints, whose value is always below the primal
  4. A problem with the same number of variables and constraints as the primal, but reversed signs
Answer and working

A. A minimisation with 'greater than or equal to' constraints and the same optimal value

For a standard maximisation primal, the dual minimises the resource values subject to ≥ constraints, one per primal variable. At optimality the objective values are equal (strong duality). The dual has as many variables as the primal has constraints.

Question 9 · easy

In a transportation problem, total supply from the depots is 900 t and total demand at the markets is 750 t. What is done before solving?

  1. Add a dummy market with a demand of 150 t and zero transport cost
  2. Add a dummy depot with a supply of 150 t and zero transport cost
  3. Reduce every depot's supply in proportion until supply equals 750 t
  4. Solve as it is, because the method works with unequal totals
Answer and working

A. Add a dummy market with a demand of 150 t and zero transport cost

Supply exceeds demand by 150 t, so a dummy destination with demand 150 t and zero cost absorbs the surplus; goods 'shipped' to it are simply not shipped. A dummy source is used when demand exceeds supply.

Question 10 · medium

Which method for an initial transportation solution uses penalties, the difference between the two lowest costs in each row and column?

  1. Vogel's approximation method
  2. The north-west corner rule
  3. The modified distribution (MODI) method
  4. The stepping-stone method
Answer and working

A. Vogel's approximation method

Vogel's method allocates first to the row or column with the largest penalty, which gives a starting solution close to optimal. The north-west corner rule ignores costs; MODI and stepping-stone are used to test and improve a solution, not to start one.

A study plan for Engineering Economics, Project & Business Management in ICAR AICE-JRF/SRF

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (71% of the 42 questions): Linear programming (11, 26%); Project appraisal and detailed project reports (10, 24%); CPM and PERT (9, 21%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Break-even analysis (3, 7%); NPV, IRR, benefit-cost ratio and payback (3, 7%); Replacement analysis (3, 7%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Depreciation methods (1, 2%); Fixed and variable costs (1, 2%); Time value of money (1, 2%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Depreciation methods (1 hard of 1), Break-even analysis (2 hard of 3), NPV, IRR, benefit-cost ratio and payback (2 hard of 3).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: Linear programming (4 easy of 11); Break-even analysis (1 easy of 3).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — ICAR AICE-JRF/SRF Engineering Economics, Project & Business Management

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.