LAISHA
Open Laisha

GATE Watershed Hydrology: practice questions

GATE — Agricultural Engineering (AG) · India · IITs and IISc on rotation (2027: IIT Madras)

Original practice questions written to the published syllabus · not past papers
10worked here, free
57written to this exam in this subject
13syllabus units

About GATE

GATE — Agricultural Engineering (AG) is a postgraduate admission exam run by IITs and IISc on rotation (2027: IIT Madras), for candidates in India. Computer-based, 3 hours, 100 marks (15 General Aptitude + 85 technical: 25 one-mark and 30 two-mark questions). MCQ, MSQ and NAT; negative marking on MCQ only (−1/3 for one-mark, −2/3 for two-mark); no partial credit on MSQ. On-screen virtual calculator.

Source: gate2027.iitm.ac.in.

Checked against the exam body's published information. Formats and fees change; confirm the current edition there before you book.

Watershed Hydrology in GATE

Numerical questions in the Soil and Water Conservation section: unit hydrograph and S-curve ordinates, rain-gauge network size and missing data, rational method and SCS curve number runoff, φ-index and Horton infiltration, Muskingum coefficients and reservoir routing, return period and risk. Answers are often numerical-answer-type, so units and rounding must be right.

Rain to runoff: measuring precipitation, subtracting losses, estimating runoff and routing floods.

Our 57 GATE questions in this subject: 8 easy, 34 medium, 15 hard, across 13 units.

10 practice questions, worked

Choose an answer, then open the working. Each explanation says why the right answer is right and why the others are not.

These 10 were written to GATE and are not shown on any other exam's page.

Question 1 · medium

In hydrograph analysis, 'effective rainfall' means:

  1. the total rainfall measured at the gauge
  2. rainfall that infiltrates and recharges groundwater
  3. rainfall that becomes direct runoff
  4. rainfall minus evaporation over the year
Answer and working

C. rainfall that becomes direct runoff

Effective rainfall (rainfall excess) = total rainfall − abstractions, and its depth equals the direct runoff depth. Rain that recharges groundwater is an abstraction from storm runoff, not effective rainfall.

Question 2 · easy

The probability that a 50-year flood is equalled or exceeded in any one year is:

  1. 0.64
  2. 0.02
  3. 0.98
  4. 0.36
Answer and working

B. 0.02

p = 1/T = 1/50 = 0.02. 0.98 is the probability of non-exceedance; a 50-year event is not guaranteed once in 50 years. 0.64 is the chance of at least one exceedance in 50 years (1 − 0.98⁵⁰), and 0.36 is the chance of none (0.98⁵⁰).

Question 3 · hard

A spillway must have no more than a 10% risk of its design flood being exceeded during a 50-year life. The minimum design return period is about:

  1. 500 years
  2. 10 years
  3. 50 years
  4. 475 years
Answer and working

D. 475 years

T = 1/[1 − (1 − R)^(1/n)] = 1/[1 − 0.9^(1/50)] = 475 years. 500 years comes from the approximation T = n/R, which is close but not exact. 10 years is simply 1/R, ignoring the 50-year life.

Question 4 · hard

Horton's parameters for a soil are f₀ = 50 mm/h, fc = 8 mm/h and k = 3 h⁻¹. The cumulative infiltration in the first hour, with rainfall always exceeding capacity, is:

  1. 21.30 mm
  2. 10.09 mm
  3. 13.30 mm
  4. 50.00 mm
Answer and working

A. 21.30 mm

F = fc t + (f₀ − fc)(1 − e^(−kt))/k = 8 + (42/3)(1 − e⁻³) = 21.30 mm. 10.09 is the rate at 1 h, not the depth; 13.30 omits the fc·t term. 50.00 mm takes f₀ for the whole hour.

Question 5 · hard

The longest flow path in a small watershed is 1,200 m with a fall of 18 m. The time of concentration by Kirpich's formula tc = 0.01947 L^0.77 S^−0.385 (tc in min, L in m) is about:

  1. 0.11 min
  2. 3.9 min
  3. 23.0 min
  4. 0.38 min
Answer and working

C. 23.0 min

S = 18/1200 = 0.015; tc = 0.01947 × 1200^0.77 × 0.015^−0.385 = 0.01947 × 234.9 × 5.037 = 23.0 min. Entering L in km gives 0.11; entering the slope as a percentage (1.5) gives 3.9. 0.38 is the correct time converted to hours (23.0/60) but labelled minutes.

Question 6 · medium

Urbanisation of a small catchment doubles its runoff coefficient and, by shortening tc, raises the design intensity from 50 to 70 mm/h. By the rational method, the peak increases by a factor of:

  1. 2.0
  2. 1.4
  3. 3.4
  4. 2.8
Answer and working

D. 2.8

Q ∝ C × i, so the factor is 2 × (70/50) = 2 × 1.4 = 2.8. 2.0 ignores the change in tc; 1.4 ignores the change in C; 3.4 adds the factors.

Question 7 · easy

For a curve number of 80, the potential maximum retention S in SI units is:

  1. 63.5 mm
  2. 317.5 mm
  3. 2.5 mm
  4. 12.7 mm
Answer and working

A. 63.5 mm

S = 25400/CN − 254 = 317.5 − 254 = 63.5 mm. 317.5 forgets to subtract 254; 2.5 is the inch value (1000/80 − 10) mis-labelled in mm; 12.7 mm is Ia = 0.2S.

Question 8 · hard

A watershed has CN = 70 for AMC II. Using CN(III) = CN(II)/(0.427 + 0.00573 CN(II)), the curve number for wet antecedent conditions (AMC III) is:

  1. 50.6
  2. 70.0
  3. 84.5
  4. 58.0
Answer and working

C. 84.5

CN(III) = 70/(0.427 + 0.4011) = 84.5. 50.6 is CN(I) for dry conditions; wet soils must raise, not lower, the CN. 58.0 multiplies by (0.427 + 0.00573 CN) instead of dividing.

Question 9 · medium

For baseflow separation, the end of direct runoff is often taken N days after the peak, with N = 0.83 A^0.2 (A in km²). For a 1,500 km² catchment, N is about:

  1. 4.32 days
  2. 3.58 days
  3. 32.1 days
  4. 9.00 days
Answer and working

B. 3.58 days

N = 0.83 × 1500^0.2 = 0.83 × 4.317 = 3.58 days. 4.32 drops the 0.83 (it is the original formula for area in square miles). Using A^0.5 gives 32.1 days, and entering the area in hectares (150,000) gives 9.00 days.

Question 10 · medium

By Snyder's method a basin has lag tp = 11 h, so the standard duration is tr = tp/5.5 = 2 h. For a 4-hour unit hydrograph, the adjusted lag is:

  1. 11.0 h
  2. 11.5 h
  3. 13.0 h
  4. 12.0 h
Answer and working

B. 11.5 h

tpR = tp + (tR − tr)/4 = 11 + (4 − 2)/4 = 11.5 h. 13.0 adds the whole difference in duration; 11.0 ignores the adjustment. 12.0 h divides the duration difference by 2 instead of 4.

A study plan for Watershed Hydrology in GATE

This plan follows where our questions actually fall, so the time goes where the marks are likely to be. It is our reading of the syllabus, not the exam body's weighting.

  1. First, the heavy units (53% of the 57 questions): Hydrographs and the unit hydrograph (8, 14%); Infiltration: Horton, Philip and the phi-index (6, 11%); S-curve, IUH and synthetic unit hydrographs (6, 11%); Flood routing: Muskingum and reservoir (Puls) methods (5, 9%); Frequency analysis, return period and IDF curves (5, 9%).

    Read the manual chapters for these first and do every worked question you can find on them.

  2. Then the middle band: Missing rainfall data and double-mass analysis (4, 7%); Precipitation measurement and rain-gauge networks (4, 7%); Runoff estimation: rational method (4, 7%); Runoff estimation: SCS curve number (4, 7%); The hydrologic cycle (4, 7%).

    Aim for one sitting per unit, then mixed questions across them.

  3. Then the lighter units: Interception and evaporation (pan) (3, 5%); Streamflow measurement (3, 5%); Drought classification (1, 2%).

    Learn the definitions, classifications and standard numbers; these units are more often recalled than worked.

  4. Leave time for the hard ones: Flood routing: Muskingum and reservoir (Puls) methods (2 hard of 5), Frequency analysis, return period and IDF curves (2 hard of 5), Infiltration: Horton, Philip and the phi-index (2 hard of 6).

    Come back to these after a first pass, untimed, and read every explanation, including for the options you rejected.

  5. Bank the easy marks: The hydrologic cycle (2 easy of 4); Hydrographs and the unit hydrograph (2 easy of 8).

    Do these early in revision so they are fast on the day.

  6. Finish timed. Sit the subject as a timed set without notes, mark it, and send each wrong answer back to its unit above.

Last updated · How Laisha writes and checks its pages · Report a mistake

Ask Laisha about this

Opens Laisha's chat with your question ready to send. Sign in or start free.

Unlock every question — GATE Watershed Hydrology

US$10 a month · one price worldwide · cancel any time

  • Every practice question in this subject, with full working
  • Timed exam papers and progress by unit
  • Ask Laisha to explain any answer — up to 1,000 questions a month
Free or Smarter
FreeSmarter
Grow guides, pest pages, articlesRead allRead all
Ask Laisha5 a dayUp to 1,000 a month
Exam practiceThe sample on each pageEvery question, timed papers
Crop calendar and pest alerts—For your own fields
Calculators and tools—All
Uploads and reports—100 a month, real files
10 days free for every new account, no card.